Vietnam is building new connections to buy more electricity from southern China, as its government tries to avert shortages in the north. Its system operator and two Chinese grid companies agreed on 21 January 2026 to raise purchases on the Lào Cai link to 600 MW this year and to open a 220 kV line from Guangxi to Móng Cái in 2027, the newspaper Nhân Dân reported. Construction of a 220 kV substation at Móng Cái began on 27 September 2026.1 2 8
What flows today
China supplies a small part of Vietnam's power. A draft of Vietnam's revised power development plan, reported by The Investor in February 2025, put imports from China at about 550 MW, carried mainly in the dry season over two 220 kV lines, Malungtang to Hà Giang and Maquan to Lào Cai, for 2 to 3 billion kWh a year. The same report said Vietnam's total imports from China and Laos were 5 billion kWh in 2024, and that they had fallen to about 1.4 billion kWh in 2021 when supply from China was temporarily halted.3
Imports are rising quickly overall. EVN, the state utility, put electricity imports at 7.21 billion kWh in January to July 2026, up about 69% on a year earlier and 3.5% of total supply, the newspaper Tiền Phong reported. It gave no split between the two suppliers.4
Việt Nam hiện nhập khẩu điện chủ yếu từ Lào và Trung Quốc.
Vietnam currently imports electricity mainly from Laos and China.4
Laos is the larger and faster-growing source. By the end of 2025 Hanoi had approved imports from 47 Lao projects with 8,260 MW, of which 2,379 MW was operating, Tiền Phong said.4
The plans for China
The revised plan aims for about 3,000 MW more from China, connected at Lào Cai and Quảng Ninh, an official of the trade ministry's Institute of Energy told a conference in November 2025, according to the business site Người Quan Sát. EVN was also considering buying a further 3,000 MW through a station on the border, producing about 15 billion kWh a year, The Investor reported, describing it as a proposal still under consideration.5 3
The January meeting brought together Vietnam's National System Operator (NSMO), Lancang-Mekong International (CSG-LMI), a unit of China Southern Power Grid, and Yunnan Power Grid. Beyond the 600 MW target for the Guman to Lào Cai direction and the Guangxi to Móng Cái line, the parties agreed to study a larger 500 kV link through a back-to-back station in 2026 to 2030. A back-to-back station converts power to direct current and back, so that two grids can trade without running in step.1
The lines being built
The Vietnamese side has started the grid works these imports need. The 500 kV Lào Cai to Vĩnh Yên line, 229.5 km long and costing more than 7,410 billion dong, was energised on 30 September 2025. VnEconomy reported that the line can carry about 3,000 MW and raises the capacity to receive imported power.6
At Móng Cái, on the border with Guangxi, the 250 MVA substation will cost 482.93 billion dong and is due for completion in the second quarter of 2027, the procurement newspaper Báo Đấu thầu reported. It says the station will help relieve capacity for electricity imported from China. Tạp chí Công Thương listed the substation among four related projects, including a 220 kV border line, that were still completing investment procedures at a provincial meeting on 8 September 2026.2 7
In April 2026 Prime Minister Lê Minh Hưng ordered more imports from Laos and China and faster grid projects, so that northern Vietnam could receive more imported power as early as 2027, Tuoi Tre reported.8
The Chinese account
China Southern Power Grid presents its cross-border trade as clean-energy co-operation. Its account at the COP30 climate conference in November 2025, reported by China News Service, gives regional totals and does not name Vietnam separately.9
与澜湄国家建成16条110千伏跨境互联线路,累计电力贸易量超过800亿千瓦时,清洁能源占比超过90%。
It has built 16 cross-border lines of 110 kV with the Lancang-Mekong countries, with cumulative power trade above 80 billion kWh, over 90% of it clean energy.9
No contract price for Chinese power was found in the Vietnamese or Chinese sources read. For Lao plants, Vietnam has set ceilings of 6.95 US cents per kWh for hydro and wind power.4
What to watch
The 2026 target of 600 MW on the Lào Cai link and the Guangxi to Móng Cái line for 2027 are the next tests. No published figure yet shows how much of this year's import growth came from China.1 4