Goods worth $107.23 billion were declared through the customs region that covers Lang Son, Vietnam's main road gateway to China, between 1 January and 31 October 2026, up 38.15% on a year earlier, Vietnam's state radio reported on 5 November. Imports, at $74.23 billion, grew faster than exports, at $32.99 billion. The figures come as both governments build an automated freight crossing at Huu Nghi, on the Vietnamese side, and Youyiguan, on the Chinese side. China says its half is ready for trial operation. Vietnam's first phase is now due in the first quarter of 2027.1 2 3
Three gateways, three growth rates
The customs region at Lang Son collected more than 19,914 billion dong in state revenue from imports and exports in the ten months, up 87%. Imported cars and special-purpose vehicles provided about 42% of that revenue and machinery and parts about 29%.1 The flow of imported trucks was rising again in November: on 11 November, 88 trucks crossed at Huu Nghi and the dedicated freight road at Tan Thanh, and on peak days since the start of the month more than 100, according to the Dong Dang-Lang Son border economic zone board.4
Further west, trade through the Lao Cai border gates reached $3,275.7 million in the ten months, up 28.83%, according to the provincial newspaper. Exports of $1,992.23 million rose 58.89% and imports of $1,119.69 million rose 26.66%, led by dragon fruit, rambutan, durian, cassava and spices. By this site's arithmetic those two figures add up to $3,111.92 million; the article does not say what makes up the rest.5
On the coast, trade through the crossings around Mong Cai in Quang Ninh came to almost $5.7 billion, up 19%, with about 2.3 million tonnes of goods, the Vietnam News Agency reported.6
The smart crossing: China says its half is ready for trial operation
The project covers the dedicated freight roads at border markers 1088/2-1089 and 1119-1120, where containers are to be carried across by driverless vehicles and checked remotely.2 3 A reporter for the 21st Century Business Herald was told in October that the Chinese project, budgeted at 1.06 billion yuan, with about 1 kilometre of route on the Chinese side, completed a full trial with real trucks and real cargo in the outbound direction in February.3
目前中方段已具备试运行条件。
The Chinese section is now ready for trial operation.3
The newspaper puts the design capacity at 2,880 container trips a day once both sides connect, and says the crossing as a whole would then handle more than 4,000 vehicle trips a day, over twice the previous level. The traditional road crossing, which usually closes around 7 pm, would stay open for irregular cargo such as machinery.3
Chinese customs at Youyiguan have already automated parts of their work. The state-run Science and Technology Daily says vehicle waiting time fell by 20% and lab identification of pests dropped from three to five days to within 36 hours. It says the crossing cleared 620,000 tonnes of imported durian worth 17.61 billion yuan in January to August 2026, up 30.4% by volume.7
Vietnam's half: a target of the first quarter of 2027
Vietnam's government treats the pilot, approved by Prime Minister's Decision 865, as a national project. At a meeting on 19 October the standing deputy prime minister, Pham Gia Tuc, told agencies to treat it as a task for the country rather than for Lang Son alone, and set a new goal for the first phase.2
Phấn đấu hoàn thành giai đoạn 1 trong quý I/2027.
Strive to complete phase 1 in the first quarter of 2027.2
The same report says the parts not funded from the state budget are behind schedule, and that funding problems are to go to the finance ministry.2 Lang Son has already written the rules for the vehicles: a provincial decision in force since 10 August 2026 sets health checks for driverless vehicles entering at the two freight roads, with observation limited to 15 minutes a vehicle.8
Other provinces are following. Eight automated lanes have been built at the Bac Luan 1 bridge in Mong Cai, due to start in December 2026 in step with the Chinese side.6 A plan of Lao Cai's provincial party committee, reported on 16 November, aims to double freight capacity through its Kim Thanh and Ban Vuoc crossings, cut logistics costs by 20% to 30% and reach about $9 billion of trade through them by 2030.9
The next dates are the Bac Luan lanes in December 2026 and Huu Nghi's first phase in the first quarter of 2027.6 2