Thailand has set aside the full Land Bridge, a plan for two deep-sea ports joined by about 90 km of road and rail across the southern peninsula so that cargo could avoid the Strait of Malacca. A government review found the project would lose money, and on 27 October 2026 the cabinet accepted its advice to upgrade the existing Andaman Sea port at Ranong first, according to Pattaya Mail's report of the transport minister's announcement.1 2 5 9
Revived because of Hormuz
The idea is old, but it returned in 2026 for a reason tied to sea lanes. After the closure of the Strait of Hormuz, Prime Minister Anutin Charnvirakul asked for the review to be sped up, China's Global Times reported from Bangkok in April. The paper gave his reason in reported speech:1
泰国有必要推进该计划,以增强国家物流安全和自主能力。
Thailand needed to advance the plan to strengthen national logistics security and self-reliance.1
The plan as revived would link Chumphon on the Gulf of Thailand with Ranong on the Andaman coast at a cost of about 1 trillion baht, according to Reuters. An internal government presentation seen by Reuters claimed the corridor could cut logistics costs by nearly 30% and transit times by up to 14 days for cargo between southern China and Indian Ocean ports. Thai estimates put about 80% of container traffic at the main Malacca Strait ports, including Singapore, as transshipment cargo, and the head of Thailand's transport planning office told Reuters Thailand wanted to capture some of it, particularly the feeder segment of ships of 12,000 TEU (twenty-foot containers) or less.2
Eugene Mark of Singapore's ISEAS-Yusof Ishak Institute told Reuters that unloading and reloading cargo at each coast "remains a major hurdle" against the through route at Malacca.2
The review and the numbers
On 5 May 2026 the cabinet noted the National Human Rights Commission's proposals on the project and gave the transport ministry 30 days to respond. The same day Deputy Prime Minister and Finance Minister Ekniti Nitithanprapas said the prime minister had given his new study board 90 days to weigh the project, Thansettakij reported.3 Reuters, as carried by Baird Maritime on 25 July, reported that the panel's updated assessment put the project's net present value at minus 10.3 billion baht, against plus 637.7 billion baht earlier. The panel saw "no immediate need" for a new Gulf of Thailand port and called the environmental studies outdated.5
Mr Anutin denies that the plan is dead. On 27 July he said it would wait while the government builds the "missing link" rail sections first, Thai PBS reported.6
ไม่ได้พับ แต่เป็นการดำเนินการตามสถานการณ์ปัจจุบัน
It has not been shelved; it is being handled according to the present situation.6
By 9 August, speaking in Ranong, he said the Land Bridge had not gone ahead because the review found it not worthwhile, and that Ranong would be developed as the link between the Andaman Sea and the Gulf of Thailand instead, according to Krungthep Turakij.8
What replaces it
The smaller plan works on the existing route. Deputy Transport Minister Sanphet Boonyamanee said on 19 July that the ministry would work with the Marine Department to plan dredging and maintenance of the 28 km approach channel to Ranong, that the port authority is procuring more cranes, and that the ministry would consider widening Highway 4 between Chumphon and Ranong. Freight trains now stop at Saphli station in Chumphon, leaving about 110 km by truck to Ranong, so a rail extension is to be studied.4
The recommendations the cabinet accepted on 27 October, as Pattaya Mail summarises them, are to use Ranong's capacity fully, study a rail link to the national network, build a new Andaman port only if cargo outgrows Ranong; the committee found no current need for a new Gulf of Thailand transshipment port. Mr Phiphat added that deep-sea ports remain necessary on both coasts and that Ranong and Chumphon are still considered suitable sites, though scale, investment model and transport links must be reconsidered. The same report says more than 34% of goods from southern Thailand leave through ports in neighbouring countries.9
Ranong is small. The government's Thailand NOW site reported 7,000 TEU in the first seven months of fiscal 2026, up 55.56%, at a port with a 150-metre container berth. The government pitches it as a gateway to South Asia, with a planned Ranong to Chittagong service to Bangladesh.10
How the camps read the retreat
Yu Haiqiu of the China Institute of South and Southeast Asian Studies in Kunming told the Chinese site Guancha that the decision was "prudent and pragmatic" but reluctant, and that whether shipping lines would leave cheaper, established routes was "a huge commercial question", according to the China-Global South Project. Mr Mark of ISEAS called claims that Washington forced the retreat an "overinterpretation" and said the causes were domestic.7
The next step is the transport planning office's study of options to connect the two coasts, which the government has asked for but which has no published deadline.9