Long Thanh airport is set to open on 24 December, but its cargo terminals are not all ready

Vietnam's airports operator plans commercial flights at Long Thanh from 24 December 2026, six months after its earlier target. Phase one is built for 1.2 million tonnes of cargo a year, but cargo airlines want the terminals finished before they move.

Companies and supply chains 18 November 2026

Long Thanh International Airport, Vietnam's new gateway east of Ho Chi Minh City, is expected to open for commercial flights at midnight on 24 December 2026, the operator Airports Corporation of Vietnam (ACV) told Dong Nai province in a document reported on 30 October. Its first phase is designed for 25 million passengers and 1.2 million tonnes of cargo a year. The airport is to open in part from December, and some large international cargo carriers say they will move only once the cargo terminals are complete.1 4

Opening date and first flights

ACV plans up to about 366 flights a week at first, 322 domestic and 44 international. Vietnam Airlines is to fly Long Thanh to Hanoi and some international routes; Vietjet is to base three aircraft there for domestic routes from December 2026 to March 2027. Vietnam's aviation authority says the foreign airlines have all formally proposed moving their Long Thanh operations into the winter 2027 schedule, and want 6 to 9 months' official notice of the date.1 2 4

dự kiến sẽ đưa vào khai thác thương mại lúc 0h ngày 24/12/2026.

It is expected to enter commercial operation at 0:00 on 24 December 2026.1

The opening has moved back from June to December 2026. In September 2025 trade press reported a full launch in June 2026. In June 2026 ACV aimed for December, and in October it named 24 December. By 9 October Component Project 3, the essential operating works, was about 86% complete by contract value, with 4 of its 16 main packages finished, and most of the remaining packages could be finished in December, Vietnamese press reported. The aviation authority still has to inspect and license the airport.6 3 1 9

Cargo capacity

The airport is planned to reach 5 million tonnes of cargo a year when fully built. Cargo Terminal No. 1 is among the works still being finished.2 1

Vietnam's Construction Ministry chose Vietnam Airlines in September 2025 for three cargo projects: Cargo Terminal No. 2, for 550,000 tonnes a year at about 4,384 billion dong; warehouses 5 to 8, for 650,000 tonnes at about 1,015 billion dong; and an express terminal for 100,000 tonnes at about 203 billion dong.8

That plan may change. Vietnam Airlines has reported to the government proposing to adjust the timing and capacity of Cargo Terminal No. 2 to fit its actual needs, a report of 16 October says. Some large international cargo carriers and express firms say the cargo and express terminals must be fully built to technical standards before they move their operations to Long Thanh.4

các hạng mục thuộc nhà ga hàng hóa phải được đầu tư hoàn chỉnh

The cargo terminal facilities must be fully built.4

Why air cargo matters for Vietnam's exports

Vietnamese airports handled about 1.77 million tonnes of cargo in 2025, 74.7% of it international, and 920,919 tonnes in the first half of 2026. Hanoi's Noi Bai airport took about 60% of the first-half volume, the party newspaper Nhan Dan reports.5

Air carries a small share of Vietnam's cargo by weight but, Nhan Dan says, about 30% of the value of its goods trade. The same report says foreign airlines carry over 80% of Vietnam's international air cargo, and that the country aims for 4.35 million tonnes of air cargo capacity by 2030.5

đóng góp trung bình tới 30% tổng kim ngạch xuất nhập khẩu hàng hóa của Việt Nam

On average it accounts for up to 30% of Vietnam's total goods trade value.5

An official of the Trade Ministry's import-export department writes that exports of electronics, computers and components reached US$107.7 billion in 2025. He cautions that this is overall trade, not the value carried by air.7

Next

Acceptance of the main works is due in November 2026, and environmental, security and staffing approvals in early December, before the planned opening on 24 December. The government has not yet ruled on Vietnam Airlines' request to change Cargo Terminal No. 2.1 4

Sources

  1. VietnamPlus (Vietnam News Agency). Sân bay Long Thành dự kiến đưa vào khai thác thương mại từ ngày 24/12 (Long Thanh airport expected to start commercial operation on 24 December). 30 October 2026Vietnam's camp · state media · in Vietnamese
  2. VietnamPlus (Vietnam News Agency). Sân bay Long Thành dự kiến khai thác tối đa 366 chuyến bay mỗi tuần (Long Thanh airport expected to handle up to 366 flights a week). 27 October 2026Vietnam's camp · state media · in Vietnamese
  3. Báo Đấu thầu. Sân bay Long Thành phấn đấu đưa vào khai thác thương mại trong tháng 12/2026 (Long Thanh airport aims for commercial operation in December 2026). 29 June 2026Vietnam's camp · state media · in Vietnamese
  4. Đại biểu Nhân dân. Các hãng hàng không gấp rút chuẩn bị khai thác sân bay Long Thành (Airlines hurry to prepare for Long Thanh airport). 16 October 2026Vietnam's camp · state media · in Vietnamese
  5. Nhân Dân. Khơi thông nguồn lực trở thành trung tâm logistics hàng không khu vực (Unlocking resources to become a regional air logistics hub). 1 August 2026Vietnam's camp · state media · in Vietnamese
  6. Aviation Week. Vietnam Targets Long-Haul Shift To Long Thanh In 2026. 26 September 2025Independent camp · trade press
  7. Tạp chí Công Thương. Phát triển logistics hàng không, góp phần nâng cao năng lực cạnh tranh xuất nhập khẩu và chuỗi cung ứng quốc gia (Developing air logistics to raise the competitiveness of trade and national supply chains). 14 October 2026Vietnam's camp · government · in Vietnamese
  8. VCCI. Vietnam Airlines to develop 3 air logistics projects at Long Thanh airport. 11 October 2025Vietnam's camp · press
  9. CafeF (Tiền Phong). Dự án sân bay Long Thành 'chạy nước rút' (Long Thanh airport project in its final sprint). 30 October 2026Vietnam's camp · press · in Vietnamese