Vietnam's National Assembly voted on 24 August 2026, by 460 of the 473 deputies present, to revise the Lao Cai-Hanoi-Hai Phong railway, a standard-gauge freight and passenger line from the Chinese border to the port of Hai Phong. The government had asked to raise the preliminary cost from 203,231 billion dong to 289,339 billion dong, an increase of about 42%. China's Export-Import Bank has offered $6.5 billion of loans, but no loan agreement had been reported signed by mid-November.1 2 3
What was approved
The resolution, as reported by the procurement newspaper Bao Dau Thau, sets a main line of about 363 kilometres from the cross-border rail junction at Lao Cai to Nam Hai Phong station, with about 63 kilometres of branch lines. The section from Bac Hong to Nam Hai Phong and the link from Yen Vien to Gia Lam are to be double track; the rest is single track. The goal is to complete the project substantially by 2030 at the latest.1
phấn đấu hoàn thành cơ bản Dự án chậm nhất vào năm 2030
aim to substantially complete the project by 2030 at the latest1
The government's proposal of 6 August put the extra construction and equipment cost at more than 51,200 billion dong and the extra cost of compensation and resettlement at almost 34,850 billion dong, mostly because provinces updated land prices. Other changes include moving the northern passenger hub to Gia Lam, adding two branch lines and building the whole Bac Hong-Nam Hai Phong section as double track from the start.2
The Assembly's economic and finance committee warned that finishing everything by 2030 would be very difficult and asked for a fallback plan if the loans were not secured.2 Deputies discussing the bill on 6 August said about 25,000 people in six provinces would be affected and called for tighter control of foreign borrowing.4
The money: $6.5 billion from China, possibly in yuan
The business site VietnamFinance reported on 28 August that the project is now put at about $10.8 billion, of which $4.3 billion is Vietnam's own share and $6.5 billion is to be borrowed. According to the report, China Eximbank's chairman proposed splitting the loan into a concessional part and a commercial part guaranteed by Vietnam's government, and lending in yuan rather than dollars, which he said would cut interest costs and currency risk. He also suggested that Vietnam's finance ministry raise its own share through yuan bonds.3
The deputy finance minister, Nguyen Duc Chi, said the $4.3 billion was already in the 2026-2030 public investment plan, and that borrowing from Chinese lenders suited a project using Chinese technology and materials. On the yuan offer he committed to nothing.3
giữ tư duy cởi mở và đang tiếp tục nghiên cứu sâu
keeping an open mind and continuing to study it in depth3
An infrastructure trade site, Southeast Asia Infrastructure, put the revised cost at $11.05 billion on 31 August and said the financing agreement and final loan terms were not yet confirmed.5 This site found no report of a signed loan agreement in the sources read.
What China says it is building towards
China paid for the feasibility study as aid. The Chinese business daily Yicai reported on 2 April 2026 that the Commerce Ministry's international co-operation bureau had handed Vietnam's construction ministry a draft of the report, and that the first package of works, on station infrastructure, began in Lao Cai on 19 December 2025.6
老街-河内-海防铁路是双边合作的重点项目之一。
The Lao Cai-Hanoi-Hai Phong railway is one of the key projects of bilateral co-operation.6
For freight, Yicai sets out the gap the line would close. China has already rebuilt its Kunming-Hekou section to standard gauge, while trains from Yunnan into Vietnam still run on the old metre-gauge track. Trains from Pingxiang in Guangxi can run through to Hanoi on the existing dual-gauge Dong Dang line, and China-Vietnam trains from Guangxi carried 37,000 containers (measured in twenty-foot units) of exports in 2025, up 86%.6
On 25 March 2026 the two governments also signed a Chinese technical-assistance agreement to plan two more standard-gauge lines, Hanoi-Dong Dang and Hai Phong-Ha Long-Mong Cai. China said it would follow the model used for the Lao Cai line.7
What Vietnam's border province expects
Lao Cai's provincial plan, reported on 16 November, links the railway to a goal of doubling freight capacity at its Kim Thanh and Ban Vuoc crossings and reaching about $9 billion of trade through them by 2030, within a Kunming-Lao Cai-Hanoi-Hai Phong-Quang Ninh corridor.8 None of the Vietnamese sources read gives a freight forecast for the line itself.
The open question is the loan: its size, its currency and its split between concessional and commercial terms remain to be agreed.3 5