Laem Chabang, the deep-sea port on Thailand's Eastern Seaboard, is close to full. Its capacity is about 11 million TEU (twenty-foot containers) a year and it handled 10.8 million, a planning official of the Port Authority of Thailand (PAT) told Krungthep Turakij in October 2026. The phase 3 expansion meant to relieve it is 74% complete overall, but its first new berth cannot be handed over because of a technical problem with the sea fill, over which the concessionaire is claiming compensation.1 2
ท่าเรือแหลมฉบังตอนนี้ใกล้เต็มขีดความสามารถแล้ว
Laem Chabang port is now close to full capacity.1
Phase 3: what is built and what is stuck
PAT values phase 3 at 114 billion baht, of which its own share is 49 billion baht. Dredging, breakwaters and land reclamation are 98% done, utilities 29%, and the rail and equipment contracts are being procured. The new terminal is designed for ships of up to 15,000 TEU, and Pier F alone is expected to handle 7 million TEU a year.1
The berth is held up by the ground under it. Deputy Prime Minister and Transport Minister Phiphat Ratchakitprakarn said on 18 September that the relative density of the underwater fill differs between two sections of the Terminal F berth, which he called a safety risk, and that the private concessionaire was claiming about 4,000 million baht in compensation. He ordered PAT to establish who is responsible before any talks.2
ความเสียหายที่เกิดขึ้น แม้ว่ามิติไหนก็แล้วแต่ ต้องมีผู้ที่รับผิดชอบ
Whatever form the damage takes, someone must be held responsible.2
PAT says the project is planned to open in 2027, but the reclamation schedule does not yet match its joint-venture contract with the concessionaire, GPC, and any new method needs the approval of the PAT board, a contract committee and the Eastern Economic Corridor office.1
One existing operator has extended its concession. DP World's Laem Chabang International Terminal handled a record 1.9 million TEU in 2025 and won a five-year extension to operate berth B5 until April 2031, Enterprise reported. The same report gives phase 3's goal as raising the port's capacity to 18 million TEU, with Terminal F1 opening in 2027 and F2 in 2031.3
China's ambassador, Zhang Jianwei, told the transport minister in May that Beijing regards phase 3, in which Chinese companies take part, as part of wider infrastructure cooperation, according to a Thai Chinese-language report of the meeting.4
Getting boxes to and from the port
Today 90% of the port's cargo moves by road, 6% by rail and 4% by water, and the government wants rail to reach 30%, PAT says. With Pier F at 7 million TEU, at least 4 million TEU would need to go by rail, which is why PAT plans 2,000 metres of track to Pier F and 1,500 metres to Pier E.1 The minister also wants to move cargo out of Bangkok's river port at Khlong Toey and concentrate it at Laem Chabang, but PAT is still studying whether full closure is feasible.2
Some of that rail traffic would run north. Freight from Laem Chabang reaches Kunming in China in about 50 hours by rail through Nong Khai and Laos, according to figures given to the transport minister at Nong Khai and reported by Thai Post; a companion article on this site covers that route.7
The western routes got longer
The United States remained Thailand's largest export market in September 2026, at 26.5% of export value, according to Commerce Ministry data reported by The Nation. The paper also reported Nantapong Chiralerspong, director of the ministry's trade policy office, as saying that the closure of the Strait of Hormuz continued to affect Middle Eastern markets.5
That disruption reached Thai shippers early. In March, Krungthep Turakij reported that most major lines had halted bookings on Middle East, Persian Gulf and Red Sea routes, that Asia-Europe ships rounding the Cape of Good Hope instead of using Suez added about 7,500 km, and that CMA CGM was charging a surcharge of about US$2,000 per 20-foot container on some routes. The same report put Thai exports to the Middle East in 2025 at US$12,475 million, or 3.67% of the total.6
In July the Thai Chamber of Commerce said lines were calling at Khor Fakkan in the United Arab Emirates and Salalah or Sohar in Oman instead of passing through Hormuz, and that very few ships were transiting the strait.8
PAT has not set a date for handing over the Terminal F site; that step, and the approvals it needs, decide whether the 2027 opening holds.1 2