Indonesia’s INKA scheduled the last 90 kits from a 340-wagon order for November. Australian engineering company UGL placed the order, Indonesia Eximbank financed production and KiwiRail puts the wagons to work.

Companies and supply chains 18 November 2026

Of the 340 container wagons Australian engineering company UGL ordered from Indonesian train builder INKA for New Zealand, the final 90 were scheduled to leave in November. They cross the sea as kits. INKA manufactures the wagons in Indonesia, UGL supplies the technology and KiwiRail assembles them at Hillside Workshops in Dunedin. In August, the Indonesian factory had shipped 250 kits. An October profile published by INKA still gave November as the completion date.1 2

In Dunedin, the more relevant number is how many of the kits have become working wagons. Rail Minister Winston Peters announced in August that Hillside had assembled its thousandth wagon since March 2024. All of those wagons were already carrying freight around New Zealand, he said. The workshop count spans several orders and starts when a wagon rolls out of Hillside. INKA records a kit when it leaves Indonesia.1 2 3

How the supplier pays for the work

UGL has placed four wagon orders with INKA since 2021. For the latest, Indonesia Eximbank provided financing of up to US$8.5 million through its export working-capital facility and a government programme for transport equipment. The manufacturer has to buy materials and pay workers before all three batches can be shipped. A facility that covers that interval tells a reader how the order is financed. UGL’s purchase price is a separate figure that the parties did not disclose.1 4

The bank backed an earlier New Zealand wagon contract in 2024 through INKA Multi Solusi, a subsidiary. That package included US$7.7 million of financing and US$4.2 million in guarantees. The guarantee covered obligations if specified conditions arose. The full US$11.9 million therefore measured the support on offer, while only the financing component provided credit that the manufacturer could draw on to do the work.4

What crosses the wharf

INKA shipped the first 130 kits in March. Another 120 left through Surabaya’s port terminals in August. Both loads were for the shorter model. The November schedule called for 40 more of that type, built for 40-foot containers, and all 50 kits in the order for 50-foot containers. UGL’s four contracts cover 1,504 kits in all. By September INKA had delivered 1,294 of those kits, according to the October manufacturer interview. The two totals give a sense of how much work the Australian buyer has placed with Indonesia beyond the November batch.1 2

Hillside can turn out up to two wagons a day. The first thousand took about 4,000 wheelsets and more than 8,000 quality-assurance check sheets. At the August milestone about 60 people worked in mechanical engineering and wagon assembly there. KiwiRail maintains roughly 4,400 freight wagons across its network. Each kit delivered from Java keeps some of the work of renewing that fleet in Dunedin, from bolting together the components to checking a finished wagon before it carries its first container.2 3 5

Sources

  1. PT Industri Kereta Api. INKA Kirim Tambahan 120 Unit Gerbong ke Selandia Baru [INKA sends 120 more wagons to New Zealand]. 20 August 2026Industry camp · manufacturer shipment announcement · in Indonesian
  2. ROLLINGSTOCK via PT Industri Kereta Api. Made in Indonesia: PT INKA in focus. Interview with Bambang Jatmika and in-depth profile. 28 October 2026Independent camp · railway industry interview
  3. New Zealand Minister for Rail. 1,000th wagon shows Hillside is back at work. 18 August 2026New Zealand's camp · ministerial statement
  4. Indonesia Eximbank. Indonesia Eximbank Dukung Kembali Ekspor Gerbong Kereta Barang ke Selandia Baru, Perkuat Daya Saing Industri Strategis Nasional [Indonesia Eximbank renews support for freight wagon exports to New Zealand]. 4 August 2026Indonesia's camp · state export finance agency · in Indonesian