Trade War

What Taiwan's home-built Hai Kun submarine imports, and whose permission it needs

Taiwan's Hai Kun submarine relies on a US combat system and US torpedoes, and Korean courts have convicted men who sent it torpedo-tube designs without a licence. A year late, it is still in trials.

Companies and supply chains 23 November 2026

Taiwan's Hai Kun, the prototype of its indigenous defence submarine, left dry dock in Kaohsiung on 17 November 2026, a year after it was due to be handed to the navy, and is expected to begin deep-dive and endurance tests, the Liberty Times reports.1 9 Although built at home by the state-controlled shipbuilder CSBC, the boat depends on foreign systems, foreign expertise and other governments' export decisions, and its schedule has been shaped by all three.2 3 4

The parts that come from abroad

The combat system and the main weapons are American. The War Zone, a US defence site, reported at the boat's launch in September 2023 that Lockheed Martin supplies the combat mission systems and that the US is to supply Mk 48 torpedoes and Harpoon anti-ship missiles.2 Those details are three years old; Taipei and Washington have not published a full equipment list.

The torpedoes are late. A written report from Taiwan's defence ministry to the legislature, summarised by the Taiwanese tech site soft4fun on 21 November 2026, says four Mk 48 training rounds arrive by the end of 2026 and 24 live torpedoes in 2027 and 2028, each costing more than NT$100 million. The ministry now expects to close the case in 2030, two years later than planned, and blames wider international production-line problems, including the time needed to restart production lines.3

Other parts are bought from foreign makers that Taiwan does not name. Su Tzu-yun of the Institute for National Defense and Security Research, a think tank under the defence ministry, said in October that the periscope's manufacturer delivered seven to eight months late.4 The Economic Daily News reported that CSBC resolved system integration problems with "technical assistance from the original manufacturers".5

Foreign people, and a Korean prosecution

Taiwan recruited outside help to design the boat. The War Zone, citing Reuters, reported in 2023 that engineers and former naval officers from Australia, Canada, India, Spain and South Korea took part, and that the UK was among at least six countries that helped; it noted that the reports could not be confirmed.2

The Korean link has since reached the courts. Prosecutors in Changwon, South Korea, say the owner of a Korean defence firm passed hundreds of classified submarine files taken from Daewoo Shipbuilding, including torpedo-tube manufacturing drawings, to Taiwan in three transfers between October 2019 and September 2020, under a US$110 million contract signed with CSBC in August 2019.6 The appeal court reduced his prison term to two years and fined his company 5 billion won, with forfeiture of about 91 billion won; four former employees of Daewoo Shipbuilding, now Hanwha Ocean, received suspended sentences.6 7 Prosecutors announced on 8 September 2026 that they had appealed to the Supreme Court. Newsis described the case as follows.6 7

국내 잠수함 핵심 기술 자료를 정부 허가 없이 대만에 유출한 사건

A case of leaking core domestic submarine technology data to Taiwan without government permission.7

The use of Korean consultants is also contested in Taiwan. Kuomintang legislator Hsu Chiao-hsin and two commentators accused former naval adviser Kuo Hsi of leaking submarine details, citing a recording of him with Korean consultants, and one commentator called former programme head Huang Shu-kuang a graft offender; on 14 August 2026 Taipei prosecutors declined to indict them, finding they commented in good faith on a public matter, and did not indict the Korean consultant accused of making the recording because the complaint was filed too late.8

Delays, cost and the frozen budget

The Hai Kun was due for handover in late November 2025; NOWnews puts its cost at NT$50 billion.9 The War Zone reported a price of about US$1.54 billion in 2023.2 In September 2026, Kuo Hsi, a former naval adviser, alleged that the boat's side-scan sonar could not feed data to the combat system; CSBC said it would not respond.10 The boat made its 25th sea outing on 15 October, then spent more than a month in dock.4 5 1

The legislature has tied money for seven more boats to the prototype. In May 2026, Kuomintang legislator Ma Wen-chun proposed freezing the whole NT$11.95 billion 2026 budget for follow-on boats. CSBC warned that a freeze could lead foreign partners and suppliers to lose confidence and withdraw.9 Defence Minister Wellington Koo answered that the ministry would seek the money once trials end.9

一旦完成海測,國防部當然就希望能夠爭取相關的預算。

Once the sea trials are complete, the defence ministry will of course hope to secure the related budget.9

TVBS reported in August that NT$12.9 billion across the 2025 and 2026 budgets stays frozen until the Hai Kun finishes its trials, the ministry reports to the legislature and legislators approve.11 No handover date has been announced; the deep-dive test and the first Mk 48 training rounds, due by the end of the year, are the next steps.

Sources

  1. Liberty Times. 獨家》潛艦海鯤號出塢了!台船碼頭6艘「超級」海洋戰隊齊聚影像曝 (Exclusive: Hai Kun leaves dock; images of six vessels at the CSBC pier). 17 November 2026Taiwan's camp · press · in Chinese
  2. The War Zone. Taiwan Launches First Domestically Built Submarine. 28 September 2023United States' camp · press
  3. soft4fun. 軍事科技|MK-48重型魚雷年底抵台 海鯤號、海龍級潛艦戰力拼圖 (Military tech: MK-48 heavy torpedoes reach Taiwan at year end). 21 November 2026Taiwan's camp · press reporting the ministry · in Chinese
  4. Liberty Times. 國造潛艦最大挑戰曝光 後續7艘恐卡政治與預算 (The home-built submarine's biggest challenges; seven follow-on boats may stall on politics and budget). 16 October 2026Taiwan's camp · press · in Chinese
  5. Economic Daily News. 潛艦海鯤號今19次出海 軍事專家:邁入深潛與長時間耐航階段 (Hai Kun goes to sea again; analyst says it enters deep-dive and endurance phase). 15 October 2026Taiwan's camp · press · in Chinese
  6. CBS Nocut News. 잠수함 기술 대만 유출 '900억대 추징'…검찰, 법인 부과 불복 상고 (Submarine technology leaked to Taiwan: prosecutors appeal 90 billion won forfeiture imposed on company). 8 September 2026South Korea's camp · press · in Korean
  7. Newsis. 창원지검, 잠수함 기술 무허가 대만 유출 사건 상고 (Changwon prosecutors appeal case of unlicensed transfer of submarine technology to Taiwan). 8 September 2026South Korea's camp · press reporting prosecutors · in Korean
  8. ETtoday. 潛艦國造爆洩密貪污!韓商內鬨「100分鐘音檔」鑑定結果出爐 (Submarine leak and graft claims: forensic result on the Korean consultants' 100-minute recording). 14 August 2026Taiwan's camp · press · in Chinese
  9. NOWnews. 海鯤號交艦延宕!馬文君提凍結後續艦119億預算 顧立雄說話了 (Hai Kun handover delayed; Ma Wen-chun proposes freezing NT$11.9 billion follow-on budget; Koo responds). 21 May 2026Taiwan's camp · press · in Chinese
  10. Liberty Times. 潛艦海鯤號預計10/10交艦?前海軍顧問:不要搞假交船 (Hai Kun handover on 10 October? Former naval adviser: no fake handover). 14 September 2026Taiwan's camp · press · in Chinese
  11. TVBS. 海鯤號衝刺倒數!想解凍129億潛艦後續艦預算 這件事超關鍵 (Hai Kun's final sprint: what is key to unfreezing NT$12.9 billion for follow-on boats). 1 August 2026Taiwan's camp · press · in Chinese

All articles