Trade War

ArticlesCompanies and supply chains

The Great Sea Interconnector: a Greece-Cyprus power cable with an Israeli leg still on paper

Seabed surveys for the Greece-Cyprus power cable resumed in November 2026 under rival Greek and Turkish notices, and Cyprus has started its first €25 million payment. The Israeli leg has only reached the regulators.

9 sources

Seabed surveys for the Great Sea Interconnector, a planned subsea electricity cable from Crete to Cyprus and later to Israel, resumed in November 2026, and Greek Prime Minister Kyriakos Mitsotakis said on 18 November that the project was going ahead "without hindrance" and on its original plan. Cyprus has begun the first of five €25 million payments it owes. The section to Israel has not gone beyond a request to the Cypriot and Israeli regulators, filed in August.1 3 4

What the cable is and who pays for it

The project, formerly called the EuroAsia Interconnector, is a high-voltage direct current (HVDC) link meant to end Cyprus's isolation as the only EU member without a power connection to the continental grid. Its first phase runs about 898 km from Crete to Cyprus, with a planned capacity of up to 1,000 MW.5 7

The French cable maker Nexans won a €1.43 billion turnkey contract in July 2023 to make and lay two 900 km cables for the Greece-Cyprus section. At that time it expected the first pole to be completed in 2028 and the second in 2029. Those dates are now out of date.7

The European Union has committed €657 million through the Connecting Europe Facility, its fund for cross-border infrastructure, according to an October 2026 opinion article by Umud Shokri in Middle East Monitor; Mitsotakis described the sum on 9 October as "over €600 million in European subsidies".5 6 The same article treats €1.9 billion as "a working estimate rather than a final bill". In the Cypriot parliament on 19 November, opposition Akel leader Stefanos Stefanou said the cost had risen from an initial €1.2 billion to €1.9 billion and that Finance Minister Makis Keravnos had put it as high as €3 billion.2 5

In August 2026 Greece's grid operator IPTO (ADMIE) signed an agreement under which the French infrastructure investor Meridiam is to take 66% of the project company, with IPTO keeping the rest. Greek business daily Mononews reports that the deal still has to be finalised and that both companies are in talks with the European Investment Bank and the National Bank of Greece on financing.3

The dispute inside the project

The 2025 and 2026 delays came as much from Nicosia as from the sea. Under a September 2024 agreement Cyprus is to pay €25 million a year for 2025 to 2029, capped at €125 million, to keep IPTO's finances steady during construction. Mononews reports that Cyprus's energy regulator approved the 2025 amount but the payment was held while Keravnos voiced doubts about the project's viability, and that Nicosia then tied it to a Greek notice for the surveys to resume.2 3

Η καταβολή των 25 εκ. από την Κύπρο που πλέον δρομολογείται, σηματοδοτεί την επιστροφή του έργου στην κανονικότητα.

The payment of the €25 million from Cyprus, now under way, marks the project's return to normality.3

On 9 December 2025 Nexans answered Cypriot press reports about the contract, saying it was still executing the project, that milestones on projects of this size can be changed, and that payments received so far had funded the cable's manufacture and eliminated its financial exposure if the project were adjusted.8 Akel's Stefanou said on 19 November 2026 that Cyprus had not been consulted on Meridiam's majority stake.2

Turkey and the surveys

Turkey holds that islands do not generate full maritime zones and claims part of the sea between Crete and Cyprus. In 2024 Turkish naval vessels escorted a survey ship working on the route away from waters Ankara claims, and Greece sent two frigates to the area.6 About 60% of the seabed surveys are done; the rest lie in the disputed area.1

The French vessel Abeille Marengo left Heraklion in November 2026 under a Greek navigational warning (navtex). Turkey then issued its own navtex saying the activity was coordinated with and consented to by Turkish authorities. The Greek government said this "does not constitute recognition" of Turkey's claim, and Cyprus's spokesman called it "of no consequence", saying no permission had been sought from Ankara.1 On 22 October Turkish Foreign Minister Hakan Fidan had said Turkey would not object if it received written notice with coordinates, as reported by Middle East Monitor; this article has not checked Turkish-language sources for his words.5

The Israeli leg and what it would mean for Israel

The Cyprus-Israel section would be a 1,000 MW, 500 kV two-way link of about 324 km at sea, laid at depths of roughly 2,200 to 2,400 m, between converter stations at Kofinou in Cyprus and Hadera in Israel. In August 2026 IPTO filed an investment request with the Cypriot and Israeli regulators, after cost-benefit studies prepared with Israel's grid operator Noga found it viable in every scenario.4

Το επενδυτικό αίτημα για τη διασύνδεση Κύπρου-Ισραήλ αποτελεί το απαραίτητο επόμενο βήμα.

The investment request for the Cyprus-Israel interconnection is the necessary next step.4

The regulators must now agree how costs are split before any final investment decision; no date has been set.4 Supporters describe Israel as an energy island whose grid has no link to its neighbours; a two-way cable would give it its first route to sell or buy electricity abroad and, Greek public broadcaster ERT reports, help it raise its share of renewable power. That is the case made by the project's backers; no Israeli government decision on the leg was found.1 4 9 Mitsotakis himself said only that the project "could eventually extend as far as Israel".6

IPTO's 2027 to 2036 plan puts completion of the Greece-Cyprus section at the end of 2031. The next scheduled step is a visit to Cyprus by Greek Energy Minister Stavros Papastavrou, provisionally on 25 November 2026.1 3

Sources

  1. Cyprus Mail. Interconnector 'progressing smoothly, without hindrance', Mitsotakis says. 18 November 2026Cyprus's camp · press reporting the governments
  2. Cyprus Mail. US reaffirms support for Great Sea Interconnector. 19 November 2026Cyprus's camp · press
  3. Mononews. Καλώδιο Ελλάδας-Κύπρου: Πώς τα 25 εκ. από την Κύπρο ξεκλειδώνουν εξελίξεις στο Great Sea Interconnector [Greece-Cyprus cable: how Cyprus's €25 million unlocks progress on the Great Sea Interconnector]. 18 November 2026Greece's camp · press · in Greek
  4. Euro2day. GSI: Αίτημα επένδυσης από ΑΔΜΗΕ σε Κύπρο και Ισραήλ [GSI: IPTO files investment request in Cyprus and Israel]. 13 August 2026Greece's camp · press reporting the operator · in Greek
  5. Middle East Monitor. A cable across contested waters: The great sea interconnector's promise and risks. 23 October 2026Pro-Palestinian advocates' camp · opinion article on an advocacy news site
  6. Cyprus Mail. Interconnector 'no longer merely a Greek and Cypriot project', Mitsotakis says. 9 October 2026Cyprus's camp · press reporting the Greek government
  7. Nexans, via Yahoo Finance. Nexans wins record-breaking contract for the EuroAsia Interconnector. 19 July 2023Industry camp · company statement