Elektroprivreda HZ HB, one of Bosnia and Herzegovina's power utilities, exported about 3,500 megawatt-hours of electricity to the European Union in the first nine months of 2026, roughly 83% less than the 20,500 MWh of the same period of 2025. The company gave the figures to the Bosnian news site Hercegovina.info, which published them on 7 November.1
The utility said the EU's Carbon Border Adjustment Mechanism, CBAM, has cut the prices and revenue it achieves and changed where its power goes. CBAM is the EU charge on the carbon emitted in making certain imports, electricity among them. The company also said CBAM was not the only cause; poor hydrological conditions and unpredictable energy markets played a part.1
Time se premija koju bi izvoz inače donosio u određenim slučajevima pretvara u neto gubitak.
In certain cases, this turns the premium that exports would otherwise bring into a net loss.1
Why hydropower is charged at the national default rate
The company's figures are new; an earlier article on this site covered the levy's effect on Bosnian steel.
Under the EU rules, imported electricity is normally charged using a default emissions value for the country of origin, not the emissions of the plant that produced it. Actual emissions can be used only if conditions in Annex IV of the CBAM regulation are met, the Energy Community Secretariat notes.2 Hercegovina.info lists those conditions as a purchase agreement, a direct connection to the EU transmission system or proof that no grid congestion blocked the route at the time, matching of output to allocated cross-border capacity, and an accredited verifier's sign-off.1
The utility told the site it cannot currently meet them, especially the congestion test, which depends on the transmission system rather than on any one producer. It said it has no verified emissions data yet but has begun preparing for pre-verification.1
Bosnia's rate is the highest in the region
The Secretariat's third-quarter report, dated 30 October, puts Bosnia and Herzegovina's default value at 1.148 tonnes of CO2 per MWh, the highest of the eight suppliers in its table. At the quarter's certificate price of €82.32 per tonne, that gives an indicative cost of €94.50 per MWh, up from €86.42 in the second quarter. Serbia's figure is €85.70 and Albania's is zero. The Secretariat says these costs are indicative.2
The Secretariat found that commercial exchange between Croatia and Bosnia and Herzegovina fell in both directions on a year earlier. Bosnia was a net scheduled importer on that border but a net physical exporter, and physical flows from Bosnia into Croatia were almost three times the scheduled exchange. It says price and trade changes cannot be put down to CBAM alone.2 Citing the report, Hercegovina.info gives scheduled exchange from Bosnia to Croatia as 490 gigawatt-hours in the third quarter of 2025 and 262 GWh in 2026, about 47% lower.3
Entity-level data also show a fall. Jabuka.tv, citing first results from the statistics institute of the Federation of Bosnia and Herzegovina entity, reported electricity exports from the Federation of 615 GWh in January to September, against 1,234 GWh a year earlier.4
Where the power goes now
The company said contracted electricity is going less to Croatia and more to non-EU markets in the region. EU buyers have not formally asked to change contracts, but they price the CBAM cost into their bids. It confirmed lower revenue without giving an amount.1
It said it has raised the issue with the European Commission, the EU ambassador to Bosnia and Herzegovina, members of the European Parliament, and state and Federation ministries. It expects the pressure to continue in 2027 and warns that it could hold back new renewable investment in Bosnia.1
The Commission's 2026 report on Bosnia and Herzegovina, published on 4 November, says only "limited action" has been taken to address CBAM, although a broad campaign on CBAM was run across the country.5 Hercegovina.info says it put questions on 4 November to Bosnia's Ministry of Foreign Trade and Economic Relations about the economic effects and planned measures. The two Hercegovina.info reports read for this article do not include an answer.1 3
The Secretariat's monitoring is quarterly, and the October report was its third of 2026. The open question for the utility is whether it can meet the verification and congestion conditions so that its hydropower is charged on actual emissions.1 2