Trade War

Zambia's TAZARA export route advances while full concession conditions remain outstanding

Railway works and Chinese financing arrangements are progressing, but TAZARA's October board review still identified conditions before the concession takes full effect. Freight growth remains a forecast.

Companies and supply chains 17 November 2026

Zambia's eastern rail route to the sea is moving through a rehabilitation programme whose commercial handover remains unfinished. In a communiqué dated 13 October 2026, the Tanzania-Zambia Railway Authority said its board had reviewed outstanding requirements before the freight concession with China Civil Engineering Construction Corporation could take full effect, alongside equipment mobilisation and infrastructure surveys.1

The distinction matters to exporters planning shipments. TAZARA's strategy projects continued operation by the authority during the first three years, with freight rising from 110,000 tonnes in 2026/27 to 234,103 tonnes in 2028/29. Much larger volumes, beginning at 1.2 million tonnes in 2029/30, are forecast after rehabilitation and the concessionaire's takeover. These are planning assumptions, rather than newly available capacity.1

Construction and finance move on different tracks

The authority had already reported the start of construction for a training centre and operations control centre in Dar es Salaam in July 2026. The facilities are intended to develop railway skills and coordinate train movements across the network. TAZARA described them as practical steps beyond negotiations, while presenting their operational benefits as expected results after completion.2

Its account identifies the railway as jointly and equally owned by Zambia and Tanzania, connecting New Kapiri Mposhi with Dar es Salaam's port. It dates the freight concession agreement to 29 September 2025 and describes investment exceeding US$1.4 billion in infrastructure, locomotives and wagons. Signing that agreement and completing all conditions for implementation are separate milestones.2

A Chinese investor filing provides a further view of the project. Jiayou International Logistics disclosed on 2 April 2026 that it planned a US$62.15 million contribution, representing 5% of a US$1.243 billion construction-period investment arrangement. Its partners include CCECC, CMOC, a Zijin subsidiary and COSCO Shipping's Hong Kong company. The filing describes investment through a holding company with project subsidiaries in Zambia and Tanzania.3

Jiayou linked its participation to the copper-cobalt belt's eastward transport route and its own road, border and inland-port facilities. It also warned that approvals and registrations remained necessary at that stage. Its construction-period figure should therefore be read within that investment disclosure, rather than substituted without explanation for TAZARA's broader concession headline.3

A guarantee is not a completed railway

CMOC's September 2026 filing says the two project companies planned combined borrowing of up to RMB6.9608 billion from financial institutions including the Export-Import Bank of China. CMOC's board approved guarantees covering 5% of the debt, with guaranteed principal capped at RMB348.04 million. The filing describes a:4

连带责任保证

joint and several liability guarantee.4

It also says the project companies had not yet begun actual business operations as of the announcement. The financing commitment supports implementation, but does not establish that the full loan was drawn or that renewed freight services had started. The next test is whether the outstanding concession requirements and construction milestones are completed in time to deliver the projected increase in export carrying capacity.1 4

Sources

  1. TAZARA. TAZARA Board Reviews Revitalisation and Approves Plan for Operational Recovery. 13 October 2026Zambia's and Tanzania's camp · joint railway authority
  2. TAZARA. TAZARA Revitalisation Moves from Plans to Visible Action. 18 July 2026Zambia's and Tanzania's camp · joint railway authority
  3. Jiayou International Logistics. 关于与关联方共同投资坦赞铁路激活项目的公告 [Announcement on joint investment with related parties in the TAZARA revitalisation project]. 2 April 2026Industry camp · stock-exchange filing · in Chinese
  4. CMOC. 关于为参股公司提供担保的公告 [Announcement on guarantees for associated companies]. 19 September 2026Industry camp · stock-exchange filing · in Chinese

All articles