Morocco's explanatory note for its 2027 finance bill places its initial green-hydrogen portfolio in the engineering-study phase, with preliminary land reservations signed. Western Sahara Resource Watch said on 12 November 2026 that four of the six projects are in disputed Western Sahara. Its geographical assessment combines the budget's regional breakdown with other information about project sites.1 2
Planned capacity is not an export flow
The budget describes a portfolio involving five investors, with planned electrolysis capacity of 6.5 gigawatts and renewable generation capacity of 17.3 gigawatts. Its intermediate hydrogen-production target is one million tonnes annually, principally for ammonia but also synthetic fuels, steel and methanol. Those totals cover the entire portfolio, including projects outside Western Sahara. They are not reported production or export sales.1
The document says preliminary engineering work has begun and that the allocation of investment remains dependent on the studies. In the government's account, land reservation is therefore a stage towards establishing an industry, with more detailed work still required before the proposed capacity can be treated as built.1
One project separates generation from fuel production
TAQA Morocco and Moeve announced a preliminary land-reservation agreement with the Moroccan government on 5 February 2026. Their statement assigns the renewable-energy component in Dakhla to TAQA Morocco, while Moeve is to handle synthetic-fuel production and commercialisation at Jorf Lasfar. The announcement links locations across the proposed supply chain; it does not place every industrial activity in Dakhla.3
The companies described the agreement as enabling:
le lancement effectif des études de faisabilité
The actual launch of feasibility studies.3
The same statement presents the project as part of Morocco's ambition to develop renewable energy and new fuels. It is a statement of commercial intent and study responsibilities. It does not announce a completed factory, the first fuel cargo or a final schedule for deliveries to overseas customers.3
Moroccan business publication Médias24 reported on 12 June 2026 that monitoring committees had validated initial technical-study deliverables for TAQA-Moeve and ORNX. It described ORNX's intended product as green ammonia and said the projects continued their feasibility work. It also reported that Moeve's synthetic fuels were intended particularly for export. That provides a prospective product and market orientation, rather than evidence of exports already leaving the territory.4
Land allocation remains politically contested
WSRW says investors should address Sahrawi consent and the territory's legal status before proceeding. It reports that it sought clarification from investors about their allocated plots and due diligence. These are the advocacy group's objections; the Moroccan budget and company announcement present the programme as industrial development.1 2 3
The UN Secretary-General's report of 1 October 2026 describes sovereignty and self-determination as unresolved issues in negotiations over Western Sahara. The next commercial question is which projects emerge from the studies with disclosed sites, final investment commitments and identifiable customers.1 5