Ukraine's state gas company Naftogaz expects to import about 1 billion cubic metres of US liquefied natural gas (LNG) in 2026, and it now has two supply routes: through Poland and, since early 2026, through Greece.1 2 The Greek route is the Vertical Corridor, a chain of existing pipelines that carries gas north through Bulgaria, Romania and Moldova. Washington backs it as an outlet for American LNG, and the first commercial contract for US gas to Ukraine along it was signed on 30 January 2026.3
The Polish route
Naftogaz said in early February 2026 that it had received the first US LNG batch of the year, nearly 100 million cubic metres, through the Świnoujście terminal in Poland, where the gas was regasified before moving by pipeline to Ukraine. Poland's ORLEN holds the terminal capacity and sells the gas on. Naftogaz said further batches were contracted for February and March.1 Naftogaz's chief executive had earlier given the 1 billion cubic metre expectation for the year.2
The Greek route
Atlantic SEE LNG Trade, a joint venture of Greece's AKTOR (60%) and DEPA Commercial (40%), signed the first sale to Naftogaz on 30 January 2026, with BP as supplier.3 Greek press reported on 13 June 2026 that Venture Global would double the US LNG it supplies to the venture from 2030, to at least 1 million tonnes a year, about 1.4 billion cubic metres, for 20 years. The venture's chief executive, Alexandros Exarchos, said the contract shields it and its customers from spot-price swings.4 The article names Greece, Bulgaria, Romania, Moldova and Ukraine as the core route, with branches towards Slovakia and Hungary and towards North Macedonia, Albania and Serbia.4
The corridor has had commercial problems. A January 2026 report said a capacity auction had drawn no meaningful uptake.3 In the first annual auction, held on 6 July 2026 for the 2026-2027 gas year, the Atlantic SEE venture secured about 4.7 terawatt-hours a year of capacity, according to the Greek energy site powergame. The site reports that the route to Ukraine was once about three times as costly as the Polish one and is now the fourth cheapest, though it gives no cost in euros for that comparison.5
Η συμμετοχή του σχήματος δίνει ένα θετικό σήμα
The venture's participation gives a positive signal.5
That sentence is the Greek site's own assessment of the auction, not a measured result. Another powergame article puts the cost of moving gas from Greece to Ukraine at EUR 9.39 per megawatt-hour, against a target of EUR 5.85, citing the price service ICIS. It says a cut in Romanian transit tariffs is the key step.4
What each government says
Greece's energy minister, Stavros Papastavrou, said the corridor "changes the balance of power", according to the Athens paper To Vima. The US special envoy for energy integration, Joshua Volz, said the route operated "in drops" and that "this is not a charity project".3 Hungary's foreign minister at the time, Péter Szijjártó, said the corridor lacks capacity and costs 20% more than gas via the TurkStream pipeline, a claim the reporting does not verify.6 Hungary has had a new government since May 2026, and this site found no statement from it on the corridor.
What the US and the EU want
In February 2026 twelve governments of the region signed a joint statement with the United States in Washington on easing US LNG entry.6 The same Washington context includes the EU's pledge in the 2025 Turnberry deal to buy US$750 billion of American energy over three years, as US officials describe it.3 The EU's own plan to phase out Russian gas is the demand-side reason for the corridor, and To Vima notes that Hungary and Slovakia oppose it.3
What comes next
The test is whether Greek terminal capacity, Bulgarian upgrades and Romanian tariffs allow regular volumes. Greek reports expect Greece-Bulgaria capacity to reach 3.6 billion cubic metres a year by the end of 2026, and talks with Romania on supply were expected to end by the close of summer. This site found no report on its outcome.4