Trinidad and Tobago expects to complete outstanding gas-development agreements with Venezuela by the end of November 2026, energy minister Roodal Moonilal told EFE on 7 November. Technical teams were to settle remaining provisions before ministers met to sign. The process concerns potential supplies for Trinidad's gas-based industries, rather than gas already crossing the border.1
Moonilal expressed confidence that US authorisations supporting the projects would remain secure. In the Spanish-language account carried by El Diario, he said:1
Estas licencias están aseguradas
These licences are secured.1
That was the minister's assurance about authorisations. The same interview made clear that contractual work remained, including a measurement and accounting arrangement concerning Loran.1
Shell distinguishes options from construction
Shell's project portfolio, updated on 29 October, puts Dragon and Loran among its options before a final investment decision. It lists Shell's share in Dragon at 80% and in Loran at 100%. The table describes both as backfill opportunities, meaning prospective gas to support existing downstream infrastructure.2
The classification is commercially significant: neither appears in the table's group of projects under construction. Manatee and Aphrodite, both in Trinidad and Tobago, do appear in that group. A government agreement and a company's investment decision are therefore different milestones in the reported project pipeline. The portfolio does not turn the planned November signatures into a production date.2
An earlier agreement raises a records question
The energy ministry separately addressed documentation for Dragon's fiscal-measurement agreement on 20 October. State broadcaster TTT reported the ministry's statement that it could not locate original executed agreements or English-language translated versions in its records. Officials had checked records and contacted staff involved when agreements were executed in December 2023.3
The ministry did identify a January 2024 Cabinet note with a copy of the signed Spanish fiscal-measurement agreement attached. It said that copy did not resolve the absence of the original or establish that an English version had also been executed. This describes a documentary-record issue; the statement did not say no signed Spanish agreement had ever existed.3
Another supply project is further advanced
Shell's October account of Manatee provides a separate view of physical progress. The company said the platform's production structure had left Altamira in Mexico for installation on a locally manufactured support structure. It expects production to begin in 2027, with eventual peak output around 604 million standard cubic feet a day.4
Planned gas flows would travel through a 115-kilometre pipeline to Beachfield. Some would supply Atlantic LNG for export, including to European and North American customers, while the remainder would serve Trinidad's electricity and petrochemical sectors. These remain planned flows from Manatee, not evidence of Dragon deliveries.4
For the Venezuelan projects, the next stated checkpoint is completion of the outstanding agreements this month.1