Russia's replacement passenger-aircraft programme remains in testing even as Aeroflot expands its planned order book. A programme update on 5 November described pre-flight checks on the second serial MS-21-310 at Irkutsk, including flight controls, engines and reverse thrust. Production activity is therefore advancing, but an aircraft being prepared for tests is not an aircraft delivered for passenger service.1
The distinction matters because the programme's commercial commitments extend well beyond the test campaign. On 18 September, Aeroflot and Rostec companies signed for another 90 MS-21 aircraft, with deliveries scheduled between 2029 and 2032. The agreement also covers simulators, crew training and after-sales support for 22 years.2
Rostec's chief executive described the order as providing a basis for:
планомерного наращивания серийного производства
a planned expansion of serial production.2
That is the manufacturer's explanation of how a long order book supports industrial planning. It does not establish that the contracted aircraft have already been completed, or that delivery dates are immune to certification and production changes.2
Replacing components creates a separate certification task
The aircraft was originally developed with international suppliers. Interfax's report on the contract says sanctions and foreign partners' withdrawal required accelerated replacement of systems and components. Rebuilding the supply chain changes the aircraft that must be approved, rather than simply changing the name on a purchasing invoice.2
The aviation trade publication's programme chronology explains that customer delivery depends on completion of certification testing and approval of the principal change to the type certificate. It also describes software updates and ground testing on the first serial aircraft before a return to Irkutsk for cabin work. These are stages in preparing a usable product, not a count of passenger flights.1
Europe's aviation regulator describes the continuing external constraint. Its sanctions guidance prohibits covered technical assistance for aviation goods destined for Russia, including services connected with manufacture and maintenance. Holders of European production approvals cannot release covered engines or components with an EASA release certificate to customers known to be in Russia or for Russian use.3
Those restrictions extend beyond the physical shipment of a spare part. EASA says technical information and design support can also constitute prohibited assistance. A Russian manufacturing milestone consequently does not demonstrate restored access to the former European certification and support relationship.3
An additional purchase remains a proposal
On 28 October, Aeroflot chief executive Sergei Alexandrovsky said the airline was ready to begin work on a third contract for 92 more MS-21s, bringing the intended total to 200. Interfax described this as a prospective agreement. It should not be added to signed orders as though negotiations had already produced an enforceable purchase.4
For suppliers, planned demand, signed contracts and approved aircraft remain different milestones. The next test is whether certification and repeatable manufacturing turn Aeroflot's commitments into operating aircraft.1 4