Russia's Rosatom is awaiting permission for hot testing at the first unit of Turkey's Akkuyu nuclear power plant. Its industry publication reported on 16 November 2026 that successful tests could allow fuel loading in December and first electricity in January or February. These remain the company's expectations for a major overseas project.1
The publication says Rosatom:
ожидает разрешения на горячую обкатку
is awaiting permission for hot testing.1
Equipment will be tested at normal operating conditions using an external energy source and simulated fuel. This stage checks safety systems and personnel readiness before the plant begins nuclear operation. Progress towards a test therefore differs from permission to generate electricity commercially.1
The export relationship extends beyond construction
The International Energy Agency describes Akkuyu as a build-own-operate project financed and led by Rosatom. The Russian group will retain majority ownership and supply fuel throughout the plant's operating life. This creates a continuing cross-border fuel and operating relationship, rather than a construction contract ending when the equipment is installed.2
The IEA also explains the power-purchase arrangement: Turkey's state electricity company is to buy 70% of the first two units' output and 30% of the other two units' output during a fifteen-year period. The weighted average price is US$0.1235 per kilowatt-hour, excluding VAT. Remaining electricity is sold to the market.2
The agency identifies different risks on each side. Rosatom and its subsidiaries carry construction and operational risk, while dollar-denominated purchases expose the Turkish buyer to exchange-rate movements. Those contractual exposures exist even before actual generation establishes the plant's operating revenues.2
Turkey emphasises its own industrial participation
Turkish Energy Minister Alparslan Bayraktar described nuclear power as part of the country's electrification strategy at an event on 13 November. He expected Akkuyu's physical start-up within the following weeks. His statement indicates Ankara's desired timetable, not confirmation that the regulator has completed every outstanding authorisation.3
Bayraktar also said more than 300 graduates of Russian universities and colleges were working at Akkuyu and that localisation had exceeded 50%. The ministry did not define the denominator for that percentage in its account. It should therefore not be equated automatically with the share of equipment manufactured in Turkey or the nationality of all project workers.3
Readiness reviews do not establish completed power sales
World Nuclear News reports that a pre-start-up visit by the World Association of Nuclear Operators involved 17 experts from several countries. They reviewed documentation, observed staff and examined equipment and operating arrangements, including emergency preparedness. The report describes a peer review, rather than announcing a Turkish operating licence.4
The same account notes that nuclear fuel reached the site in April 2023. Delivery to a site is different from loading fuel into the reactor, just as construction capacity is different from measured electricity output. No generation total is established by that delivery milestone.4
The next test of the schedule is whether permission and successful testing allow the December fuel-loading step Rosatom anticipates.1