Romania's state nuclear company Nuclearelectrica approved the final investment decision for the Doicești small modular reactor (SMR) project on 12 February 2026, and the project company RoPower Nuclear followed the next day.1 2 The plant would use six reactors designed by the US firm NuScale, but the company's own announcement says the financing structure is still to be built.1
What was decided
Nuclearelectrica's shareholders approved the decision in Bucharest, moving the project into its third stage, called pre-EPC (the engineering work that comes before a construction contract).1 The company holds 50% of RoPower Nuclear. The plant would provide 462 MW and replace the 600 MW of the former Doicești thermal plant.1 Balkan Green Energy News reports that the other half belongs to Nova Power and Gas of the E-Infra Group, and that the six units are of 77 MW each.3
The Romanian company says pre-EPC is estimated at 15 months and will produce a budget and a contractor selection. It targets operation "at the beginning of the next decade", subject to corporate approvals and regulatory requirements.1
Adoptarea Deciziei Finale de Investiție confirmă că proiectul este pregătit să intre într-o nouă etapă.
The adoption of the Final Investment Decision confirms that the project is ready to enter a new stage.2
One reactor first
The decision is not a commitment to build all six units at once. Balkan Green Energy News reports that only one reactor would be built first for testing, and that the other five would go ahead only if the trial succeeds.3 Nuclear Engineering International, citing Romanian press, says the state would pay for the first module only, likely through a credit line of Nuclearelectrica, and that the conditions in the annexes that could stop the last five reactors have not been published. It also says continuation depends on a check of possible gas leaks at the site.4 The Nuclearelectrica release itself says only that the approval rests on "additional conditions" and does not list them.1
The American part
NuScale of Oregon is the technology provider.3 Nuclear Engineering International notes a 2020 intergovernmental agreement with the United States, ratified in 2021, and a US grant of 14 million dollars for front-end engineering announced after the site was chosen in 2022.4 None of the four pages I read names a US export-credit agency or other US lender for the construction phase. Nuclearelectrica says only that over the following six months the project would define financing mechanisms and talk to potential investors.1 Any claim that Washington will finance the plant is therefore unconfirmed here.
Costs are not settled
The estimates differ by source and by definition. Nuclear Engineering International, citing Romanian press reports of company documents, gives about 4.9 billion dollars for the whole project with a range of 20 to 30% either way, and about 600 million dollars for the pre-EPC stage.4 A Czech trade outlet puts it at roughly 6 to 7 billion dollars.5 The first figure is the project's own planning estimate as reported; the second is a press estimate with no stated basis in the pages read. Earlier plans had commercial operation of the first unit in 2033.5
What to watch
The next dated step is the end of the six-month window the company set for financing structure and investor talks, which ran out in August 2026.1 I found no later public announcement of the outcome, so it is unconfirmed whether the structure has been set. The pre-EPC stage, 15 months from the February decision, would end around May 2027.