Poland's first nuclear plant: US consortium terms agreed, contract still unsigned

Poland's state developer and the Westinghouse-Bechtel consortium agreed main terms on 23 September. Both aim to sign the full construction contract by the end of 2026, backed by US export credit.

Companies and supply chains 18 November 2026

Poland's state-owned nuclear developer PEJ and a consortium of the US firms Westinghouse and Bechtel agreed the main commercial and legal terms of the engineering, procurement and construction (EPC) contract for Poland's first nuclear plant on 23 September 2026, according to trade press. The full contract is not signed. Both sides say they aim to conclude it by the end of 2026.1 2

What was agreed, and what was not

The plant is planned at Lubiatowo-Kopalino in Pomerania: three Westinghouse AP1000 reactors with a combined capacity of 3,750 megawatts. Power magazine reports that PEJ's president, Marek Woszczyk, said the agreed terms are the basis for further detailed negotiation, and that the consortium will be responsible for construction. Bechtel's nuclear head, Dena Volovar, called the deal "a vote of confidence in American nuclear technology and know-how".2

The sources do not give the contract price, the allocation of cost-overrun risk or any penalty terms. Power magazine states no project cost. Nuclear Engineering International cites an estimated total cost of EUR 42 to 46 billion, a figure it does not attribute to a named estimator.1 2

A Polish trade site, Globenergia, reported in June that the talks cover the financial model, the split of technical and contractual risk and the role of Polish companies. Its framing of what signature would mean:

Podpisanie umowy EPC otworzy drogę do właściwej budowy elektrowni.

Signing the EPC contract will open the way to actual construction of the plant.3

US financing

Nuclear Engineering International reports that the plan is 30% public equity and 70% debt, with the debt carrying Polish State Treasury guarantees. It says export credit agencies are expected to cover 60 to 70% of that debt, and that the US Export-Import Bank (EXIM) is a principal lender.1

The American Nuclear Society reported in February 2026 that EXIM and PEJ had signed a credit agreement. It is the first phase of financing for initial engineering and environmental site work. Westinghouse's Dan Lipman called it a "first milestone" and said it sets "the stage for additional financing through EXIM". The article gives no amount.4

The timetable

One discrepancy: the American Nuclear Society article gives 2033 as the target for the first unit's commercial operation, against 2036 for grid power in the other sources. The sources do not reconcile the two dates.1 2 4

Polish suppliers

Power magazine lists Polish firms with contracts for site work, including Budimex and Doraco, and says contracts awarded to Poland-based companies for early work total about USD 250 million. Nearly 200 Polish nationals are on the project team. These are the US side's and the trade press's figures; they are not an official Polish tally.2

What to watch

The year-end target is a stated aim, not a commitment with penalties attached in any source read.1 2 Whether the full EPC contract is signed before 31 December 2026, and at what price, is the next test.

Sources

  1. Nuclear Engineering International. Key EPC terms agreed for Poland's NPP. 25 September 2026Independent camp · trade press
  2. Power. Bechtel-Westinghouse group, PEJ agree on terms for Poland's first nuclear power plant. 23 September 2026United States' camp · trade press
  3. Globenergia. Umowa coraz bliżej: kluczowy etap budowy pierwszej elektrowni jądrowej w Polsce (The agreement is getting closer: a key stage in building Poland's first nuclear plant). 29 June 2026Poland's camp · trade press · in Polish
  4. American Nuclear Society. Credit agreement advances Westinghouse-Poland partnership. 19 February 2026Industry camp · trade association news