Trade War

Hungary reviews Paks II and weighs replacing Rosatom, as a US licence covers payments

Prime Minister Péter Magyar says Rosatom did not keep to its contract on Paks II. A decision on the contractor is expected in late 2026 or early 2027, while a US Treasury licence from November 2025 covers payments to Russian banks.

Other countries 18 November 2026

Hungary's government is reviewing the Paks II nuclear expansion and considering whether to replace Russia's Rosatom as contractor, with a decision expected in late 2026 or early 2027, according to Brussels Signal's report of 22 October 2026.1 Prime Minister Péter Magyar said on 13 August 2026 that he did not see Rosatom keeping to the contract.2 Rosatom says it has received no notice of termination.1

The project and the US licence

Paks II is two VVER-1200 reactors planned beside the four Soviet-designed reactors already at Paks. A 2014 agreement gave the project to Rosatom, with a Russian state loan of up to €10 billion for 80% of the cost.4 Western sanctions on Russian banks complicated payments. On 21 November 2025 the US Treasury issued a general licence for certain Paks II transactions, including with Gazprombank, VTB Bank and the Russian central bank, according to the project company's own announcement.5 Hungary's then foreign minister said earlier that Washington was lifting sanctions on the project, and the 2025 licence text itself was not among the pages I could open.4 5 The page gave no expiry date.5

What the Magyar government says

Before taking office Magyar said Paks II might still be needed but was overpriced, and that he wanted every contract reviewed, according to the news site Telex.3 On 13 August 2026 he told a press conference that costs could double against the original sum and that the original deadlines would certainly be missed.2

Ha tartották volna a szerződést, akkor 2024-ben már működnie kellett volna Paks II.-nek.

If they had kept the contract, Paks II would already have been working in 2024.2

Magyar also cited the nuclear regulator's concerns about the Danube's flow and about environmental and cooling permits.2

What Rosatom says

Rosatom's chief executive, Alexei Likhachev, told Russian journalists on 13 August that construction had accelerated and that the company was keeping to a timetable agreed with the Hungarian client. He said the government had not contacted Rosatom.2 He said the foundation of unit 5 was about 80% complete, with 18,000 cubic metres of concrete poured.2 Brussels Signal reported that he later said Rosatom was waiting for the appraisal and that its requests for talks had gone unanswered.1

The legal and financial constraints

Brussels Signal listed several constraints:

Telex wrote in April 2026 that the first-concrete ceremony had been held on 5 February 2026 and that the state-aid approval problem left the project stalled in Brussels.3

Next steps

No decision on the contract has been published in the sources I read. The government's review of financing and cooling, and any formal notice to Rosatom, are the next points to watch. The US licence's expiry date and any renewal are unconfirmed.

Sources

  1. Brussels Signal. Hungary open to replacing Russia's Rosatom in nuclear plans. 22 October 2026Independent camp · press
  2. Világgazdaság. Magyar Péter: Roszatom nem tartotta a szerződést, Paks II átvilágítása (Magyar: Rosatom did not keep the contract, Paks II audit). 13 August 2026Hungary's camp · press reporting the prime minister · in Hungarian
  3. Telex. Akár folytatja, akár elengedi a Tisza-kormány Paks II.-t, egyik sem lesz könnyű menet (Whether the Tisza government continues or drops Paks II, neither will be easy). 21 April 2026Hungary's camp · press · in Hungarian
  4. World Nuclear News. Hungary says US sanctions exemption to help Paks II project. 30 June 2025Independent camp · trade press
  5. Paks II Zrt.. The exemption from US sanctions is now in force. 24 November 2025Hungary's camp · company, state-owned

All articles