Mozambique has reconfirmed a sovereign guarantee of up to US$2.25 billion for senior creditors of Mozambique LNG, extending its validity to match revised financial documents, Lusa reported on 27 October 2026. The documents put completion at 25 March 2029. The government says the guarantee's ceiling is unchanged.1
Financing permission affects construction before exports begin
Lusa's account of the cabinet resolution says the beneficiaries, covered obligations, applicable law and arbitration arrangements remain in place. The finance minister is authorised to issue a confirmation letter. The action therefore concerns the state's existing support for creditors, rather than a new gas-export licence or evidence that commercial output has started.1
reiteramos a mesma garantia
We reaffirm the same guarantee.1
The financing structure had already changed after a different government decision. Britain announced on 1 December 2025 that UK Export Finance would end its participation following a review of amended financing terms. Business Secretary Peter Kyle said the risks had increased since the original commitment and continued financing would not serve British taxpayers' interests. He described the decision as specific to this project.2
Britain said it would refund the premium paid as its risk exposure ended. This was a withdrawal of public financial support, not a prohibition on Mozambique selling gas. Its immediate relevance to construction was the removal of a financing participant from a project whose schedule had changed during a prolonged suspension.2
Shareholders replaced part of the external funding
TotalEnergies presented the consortium's response on 2 December 2025. It said partners had unanimously agreed to provide extra equity replacing the UK and Dutch export-credit contributions, together representing about 10% of external financing. According to the company, lenders representing the remaining roughly 90% had reconfirmed their commitments.3
The company said the original project-financing package had involved about 30 lenders and US$15.4 billion. Replacing a portion with shareholders' money changes who supplies the capital and bears the exposure. Those statements explain the announced funding arrangement at that point; they are not a current audit of cash disbursements or proof that construction risks have disappeared.3
A restart is not a shipment
In its French-language restart announcement of 29 January 2026, TotalEnergies said onshore and offshore work had resumed and the project was approximately 40% complete. It targeted gas production in 2029 and reported more than 4,000 workers mobilised, including over 3,000 Mozambicans. Those were dated company figures, not a November construction-progress update.4
The same announcement envisaged more than US$4 billion in contracts for local businesses and up to 7,000 direct Mozambican jobs during construction. These are projected domestic benefits. They should be distinguished from completed purchases, permanent operating employment and export receipts already earned.4
The March 2029 completion date in financing documents and the broader production target describe different milestones; neither, by itself, specifies when the first export cargo will leave or when the state will receive net gas revenue.1 4