Mauritania's iron-ore producer SNIM carried 14.7 million tonnes by rail in 2025 and sold the same tonnage that year. Its expansion programme aims to give the railway capacity to move 40 million tonnes a year by 2030, twice its current rating. Filling that capacity means getting ore from new inland mines onto the main line and keeping trains moving all the way to the Atlantic port of Nouadhibou.1 2 5
The company owns the railway that connects its mines around Zouérate with its ore-loading terminal. Some of the existing trains serve the Guelb El Rhein complex, where two plants process ore close to the mine. Others serve deposits such as M'Haoudatt. Adding a mine to this network requires a connection to the main track as well as room for its trains on the journey to the coast.2 3 4
Where two branch lines meet the existing railway
In November 2025, the African Development Bank and the European Investment Bank signed a US$275 million financing package with SNIM. The African lender committed US$150 million, and the European lender US$125 million with a European Union guarantee. SNIM itself is the borrower. The loans cover work on the existing route, new connections, locomotives, wagons and maintenance equipment.2
The European lender's engineering assessment shows how much of the work takes place away from the mine face. A planned 30-kilometre branch will serve El Aouj and a 12-kilometre branch will reach Atomai. The plans include stations and depots on those branches, two additional places for trains to pass on the main line and a larger maintenance workshop at Nouadhibou. A passing track lets a train move aside for another, making room on the existing route for more journeys.4
What higher volumes mean for SNIM
SNIM's 2025 accounts illustrate why the commercial return will depend on more than tonnes hauled. Higher sales volumes helped lift revenue by 2 percent to 46.64 billion ouguiyas. Net profit fell 24 percent to 8.03 billion ouguiyas. The company attributed the decline to lower iron-ore prices and higher input costs. It put its share of Mauritania's exports at 27 percent for the year.5
Keeping the line available is a separate engineering challenge. The Global Center on Adaptation identifies heat that can buckle rails, sand drifting onto the track and rising sea levels at the loading port among the risks along the 704-kilometre corridor. Its work with SNIM also covers the people maintaining the railway and operating the mines in extreme heat, including guidance on worker protection during hot spells.1
For the towns along the route, an interruption can affect access to transport, water and energy supplied by SNIM. For the company, the practical test of the expansion will come as the new branches deliver ore into the existing line. The rail tonnage and sales volume SNIM already publishes give readers a way to compare what the trains actually carry with the capacity the lenders are helping it build.1 2 5