CATL began trial production of battery cells in Debrecen on 22 September 2026, moving its Hungarian investment beyond assembling modules. The company says the trials will adjust and validate equipment before series production. That distinction matters to European carmakers: a factory testing its processes is not yet evidence that its full advertised capacity is supplying customers.1
Modules were already reaching European cars
The Hungarian operation already had a commercial role before the cell trials. CATL's Hungarian announcement in May said rented premises had assembled modules since autumn 2024. By then, those lines had produced 240,000 modules used in 60,000 electric vehicles across Europe. Assembly in a separate, newly built module facility began on 6 May 2026 after the necessary permissions were obtained.2
The company described that additional line's scale precisely:
Az új modulösszeszerelő sor éves kapacitása 5 GWh.
The new module assembly line has annual capacity of 5 GWh.2
The module milestone therefore preceded the cell milestone. Combining them into a single factory-opening date would obscure which manufacturing activity was operating and which still needed authorisation.2
Building permission preceded the production trial
Economx reported on 27 August 2026 that the county authority had granted an occupancy permit for the first cell building. Its report stressed that further regulatory and preparatory steps were still necessary before production could begin. The permission covered two lines in a complex of approximately 350,000 square metres.3
The same report put the first facility's planned annual capacity at 40 GWh and described its intended role serving European vehicle manufacturers. Those figures concern the industrial scale envisaged for the building, rather than a measured annual output achieved when the occupancy decision was issued.3
CATL's September statement subsequently said the prerequisites for trials on the first two cell lines had been fulfilled. It also reported cumulative module output of 537,000 and described 100 GWh as the capacity envisaged once all facilities were ready. Neither statement establishes that the entire development was operational.1
Customers and later phases remain separate questions
After an October factory visit, Hungarian newspaper Telex reported that CATL representatives described capacity as committed to carmakers for years ahead. They said production would mainly serve German vehicle manufacturers and identified customers near Debrecen. The newspaper reported BMW and Mercedes as previously known customers, while CATL excluded supplying BYD.4
Telex also reported that the initial chemistry would be nickel-cobalt-manganese, with lines designed to permit conversion to lithium-iron-phosphate production. The company presented that flexibility as a way of adapting to customer requirements. It was not an announcement that both chemistries were already being supplied commercially.4
Expansion remains conditional. According to the same visit report, CATL was concentrating on making the first facility work properly and would decide on the second later, amid discussions with the government. The open question is how quickly the operating trials become regular customer deliveries, and whether approval follows for the additional factories.4