Finland's icebreaker relationship with the United States has moved beyond a diplomatic commitment into signed shipbuilding contracts and physical production work. The Finnish government confirmed contracts covering four vessels built in Finland in February 2026. Yle subsequently reported that production of sections for the American programme began at Pori's Mäntyluoto yard on 23 June.1 2
The allocation matters for understanding the export opportunity. Finland's economic affairs ministry said the US Coast Guard had ordered eleven vessels overall, with seven to be constructed in the United States. Finnish yards therefore supply both complete ships and expertise supporting construction across the Atlantic. The total programme is larger than the number of vessels Finland itself will export.1
Two construction locations within one contract
Helsinki Shipyard's announcement describes Davie Defense's contract for five Arctic Security Cutters, a class of polar icebreaker. Two are to be built in Helsinki, while three will be constructed at the group's facilities in Galveston and Port Arthur, Texas. The company expects the first delivery in 2028.3
Davie said American shipbuilders would work alongside Helsinki personnel to learn from their experience. Its design is based on a platform with seven previous variants already in service. This makes the relationship partly a transfer of industrial know-how, alongside the purchase of new vessels, although the company's claimed delivery advantages remain its own assessment.3
Skilled workers are a delivery constraint
The Pori work forms part of the Helsinki-linked programme. Yle reported that the two Finnish-built vessels would use the Helsinki and Pori yards, rather than being constructed entirely at a single location. Its corrected report makes clear that the American vessels are being built in Finland and the United States, not Canada.2
Sata Shipbuilding chief executive Niko Suomela told Yle that skilled workers were difficult to recruit. The yard planned apprenticeships, with the following year expected to be particularly demanding for staffing. He said:
Tämä ala kaipaisi sellaista imagokampanjaa, että nuoret lähtisivät kouluttautumaan alalle.
This industry needs an image campaign encouraging young people to train for it.2
The American customer must prepare its bases
The Coast Guard's March memorandum directs that the first two cutters should be based in Alaska. It instructs officials to select and prepare the homeports in time for delivery, commissioning and operations. The document independently confirms the construction split between Finnish and American shipyards.4
The commandant links that decision to Alaska's proximity to the Arctic and the Coast Guard's responsibilities for navigation, maritime access and American sovereign interests. These are the buyer's stated operational reasons for acquiring the ships. With the first vessel expected in 2028, the next test is whether yard capacity, trained workers and the receiving ports become ready on compatible schedules.4 3