Trade War

EU adds 46 raw-material projects, four for rare earths; the status brings no guaranteed funding

The Commission's second list, of 9 October, takes the EU's strategic raw-material projects to 93 at home. It says they could meet its 2030 rare-earth benchmarks. Its own Q&A says the status guarantees neither EU money nor completion.

Rare earths and export controls 17 November 2026

The European Commission named 46 new "strategic projects" for critical raw materials in 16 member states on 9 October 2026, taking the total inside the European Union to 93. Four of the new projects concern rare earths for permanent magnets. The Commission says the projects selected so far could meet the EU's 2030 benchmarks for mining, processing and recycling rare earths. Its own question-and-answer paper adds that the status does not guarantee EU funding or that a project will ever operate, and it has said a further call for applications will follow towards the end of 2026.1 2

What was selected

The 46 were chosen from 102 applications in a call that closed on 15 January 2026. Of those, 92 were assessed against the criteria of the Critical Raw Materials Act, the 2024 EU law that created the scheme.1

EUobserver, an independent news site, reported that copper features in 19 of the 46 projects, a count the Commission's release does not give. Reuters named the Zinnwald lithium project in Germany, the Skouries mine in Greece and the Viscaria copper project in Sweden among those chosen.3 4

What the Commission claims for it

The Act sets benchmarks for 2030: EU capacity should cover at least 10% of annual consumption of strategic raw materials for extraction, 40% for processing and 25% for recycling. The question-and-answer paper adds a fourth aim, that no more than 65% of any strategic raw material at a relevant stage of processing should come from a single country outside the EU.1 2

According to the Commission, the 46 new projects, together with the 47 EU projects chosen in March 2025 and 13 in countries outside the EU chosen in June 2025, could meet the extraction benchmarks in full for lithium, nickel, rare earths, magnesium and tungsten, and the processing benchmarks for lithium and rare earths. The wording is conditional. For processing it puts the figure at 89% of the benchmark for cobalt, 57% for tungsten and 51% for magnesium.1

The Commission states the reason for the scheme in terms of China. Its paper says the EU depends heavily on outside countries for many of these materials, above all China.2

a dependence which has already been used against the EU by limiting their supplies on the market2

What the status does not do

Strategic status gives a project a shorter permitting procedure and help in finding lenders and buyers. The permitting limit is 27 months for extraction projects and 15 months for others, subject to conditions in EU and national law.2

It is not a grant. The Commission estimates that the 46 projects need about €21.1 billion of capital investment to become operational, to come from a mix of public and private sources. For the projects chosen in 2025 it says more than €2 billion of financial support has been mobilised through the Innovation Fund, state aid and the European Investment Bank.2

Strategic project status does not automatically mean that a project receives EU funding.2

The same paper says designation does not guarantee that a project goes into operation. Of the projects chosen in 2025, it reports that 25 have completed an environmental impact assessment, 17 have a construction permit and 22 have made significant progress towards offtake agreements, the contracts under which buyers commit to take the output.2

What critics say

EUobserver reported that the Commission's own figures show little EU money has reached the schemes selected last year. It quoted the industry commissioner, Stéphane Séjourné, as telling reporters that "the results are very tangible", citing the Keliber lithium operation in Finland, the gallium output of the Greek company Metlen and the Carester plant at Lacq in France, which recycles magnets and separates heavy rare earths. EUobserver added that all three were well advanced before they received the status in March 2025.3

The EU's auditors examined the policy before the second list appeared. In a report of 2 February 2026 the European Court of Auditors said the Act's targets are non-binding, that it is unclear how their levels were set, and that the EU "will struggle to secure the supply of the strategic raw materials it needs by the end of the decade". It said an EU mining project can take up to 20 years to become operational, and that seven of the 26 materials needed for the energy transition have recycling rates of between 1% and 5% while ten are not recycled at all.5

Reuters, reporting the October list, noted that strategic projects do not automatically receive EU funding.4

What comes next

The Commission says it will announce further strategic projects in countries outside the EU towards the end of the year, and plans another call for applications towards the end of 2026. It also says it has set up an "operational core" to prepare an EU centre for critical raw materials, whose tasks are to include stockpiling. The legal mandate for that centre still has to be agreed with the EU's law-making institutions.2

Sources

  1. European Commission. Kommission wählt 46 neue strategische Projekte für die Versorgung der EU mit kritischen Rohstoffen aus (Commission selects 46 new strategic projects for the EU's supply of critical raw materials). 9 October 2026European Union's camp · government · in German
  2. European Commission. Questions and answers on the Critical Raw Materials strategic projects. 9 October 2026European Union's camp · government
  3. EUobserver. EU puts 46 more mines and recycling plants on 'strategic' list, without closing funding gap. 9 October 2026Independent camp · press
  4. Reuters, carried by Kitco News. European Commission picks 46 new strategic critical mineral projects. 9 October 2026Independent camp · wire service