Eritrea's Dekemhare solar project has sought a further package of professional equipment after its Chinese contractor reported connecting the plant to the grid. A procurement notice republished by China's Fuxin government on 24 September 2026 set a 30 October deadline for bids. It covered operating tools and information equipment, rather than another contract to build the generating plant.1 2
The equipment order reaches beyond solar panels
The notice divides the purchase into two lots. One covers protective equipment, electrical testing instruments and laboratory tools; the other covers information technology, network cabling, videoconferencing and backup power. Eritrea's Ministry of Energy and Mines is the purchaser, using African Development Fund financing and the bank's direct-payment procedure.1
The international competition required a US$5,000 bid security for each lot and disclosure of the successful bidder's beneficial ownership in the award notice. These are conditions for selecting and paying a supplier. The published invitation does not identify an award winner or confirm that the goods have been delivered.1
Construction and operation have different milestones
China Energy International Group reported that the 30-megawatt plant reached full grid connection on 2 April 2026. It identified China Energy Engineering Group Shanxi Electric Power Construction as the engineering, procurement and construction contractor, with Energy China International overseeing the work. Its account describes a photovoltaic plant, battery storage, a substation and a transmission connection.2
Chinese energy news service CPNN subsequently described the milestone as:
全容量并网发电
Grid-connected generation at full capacity.3
CPNN's report, explicitly based on information from China Energy, put expected annual generation at 73.89 million kilowatt-hours. That is a forecast of energy production, distinct from the plant's rated generating capacity. It also described battery storage as intended to smooth fluctuations in solar output. Neither the commissioning announcement nor the forecast supplies a full year's measured generation or an audited saving on fuel purchases.3
The cross-border transaction therefore includes engineering and commissioning services as well as physical equipment. The contractor's account establishes the scope of that package, but does not break down the manufacturing origin or customs value of every component installed at the site.2
Local skills remain part of the supply chain
Eritrea's information ministry reported on 24 August 2026 that the energy ministry was expanding renewable-energy use for households, agriculture and other activities. Renewable-energy director Tesfay Gebrehiwet said foreign and national specialists had provided practical and theoretical training and that this work would continue. He also called for better understanding of the proper use of solar systems.4
Local publication Mesob Journal separately reported that the African Development Bank had described Dekemhare as supplying the national grid during a May mission. Its September account also noted the later equipment procurement. Together, those dated observations show why a functioning plant and continuing project purchases can coexist.5
The next procurement milestone is an award record identifying the selected suppliers and the equipment to be delivered, followed by evidence that the purchases support the plant's continuing operation.1