Financing completed for Britain's Vanguard wind farms on 11 November 2026 gives an important customer project firmer backing for Danish turbine supplier Vestas. RWE and KKR said financial close had been reached for Vanguard West and East. Vestas had already announced a firm order for the western project in February.1 2
This progress comes after a weaker year for Denmark's wind exports. A joint industry assessment published in April put total Danish energy-technology and related services exports at DKK116.1 billion in 2025, down 0.5%. Wind equipment declined even as district heating, bioenergy and other technologies increased.3
A specific contract, including later maintenance
Vestas's 20 February announcement covers 92 turbines of its V236-15.0 MW model, providing 1,380 MW for Vanguard West. The company is responsible for supply, delivery and commissioning. The agreement also includes comprehensive maintenance for five years followed by longer-term operational support.2
That combination gives the supplier business beyond the initial machinery shipment. However, a contract award is not a record of equipment already exported from Denmark: it describes work to be delivered through the company's manufacturing and service network.2
The project schedule has also developed. February's announcement expected commissioning in 2029. RWE's November statement now expects both Vanguard projects to be fully commissioned in 2030, with offshore construction starting in early 2027. Readers assessing the order should use that later project timetable.2 1
British support helps the buyer finance construction
The UK's National Wealth Fund committed £500 million to each wind farm, or £1 billion overall. It said its lending forms part of a £12.8 billion financing package and broadens the capital available to offshore developers. The fund is owned by the UK Treasury, making this public lending within a larger financing arrangement.4
The projects also secured Contracts for Difference in the British government's seventh allocation round. The published results identify Vanguard West's principal unit at 1,380 MW and a strike price of £91.20 per megawatt hour in 2024 prices. This is an electricity-support contract price, not the price paid for Vestas turbines.5
Export results still depend on delivery
Denmark's industry assessment described wind as 42% of the energy-technology goods export category. Its weaker performance therefore materially affected the sector total. The report's coverage of exported goods and services differs from a supplier's overseas order book.3
Dansk Industri's Troels Ranis argued that Danish businesses needed to strengthen their international position:
Den styrkeposition skal vi udvikle yderligere
We must develop that strong position further.3
RWE's latest programme puts the first Vanguard West foundation installation in the first half of 2027, followed by the eastern project. Those construction milestones will show how the newly completed financing moves towards the physical works needed before turbines can begin supplying electricity.1