Czech suppliers want clearer construction contracts for the Dukovany nuclear project. On 6 November 2026, their trade associations asked Korea Hydro & Nuclear Power, or KHNP, for a timetable and arrangements to preserve preparatory work after construction-subcontract negotiations ended.1
South Korea's industry ministry said on 13 November 2026 that it was supervising a continuity plan and the selection of a new construction contractor. Its statement maintained the targets of applying for a construction permit in April 2027 and starting construction in November 2029. Those remain project milestones, rather than completed approvals or building work.2
A cross-border contract with local suppliers
The project combines a Korean main contractor with Czech equipment, engineering and construction capabilities. A June update published by Czechia's industry ministry described existing contracts for Doosan Škoda Power's turbogenerators and Energoprojekt Praha's licensing, safety-analysis and design services. It also reported completion of geotechnical investigations and delivery of the initial conceptual design.3
That update placed the project in a preparatory phase involving design, permits and enabling infrastructure. Consequently, a signed main contract does not mean every downstream package has been settled. Different firms enter at different stages, and the commercial responsibilities of a civil-works contractor differ from those of a turbine manufacturer or engineering consultant.3
The associations said uncertainty prevented firms from preparing fully. They proposed direct Czech contracts with KHNP for site preparation and some conventional infrastructure. This was an industry proposal, not an award.1
České firmy mají potřebné zkušenosti, know-how i kapacity.
Czech companies have the necessary experience, know-how and capacity.1
South Korea's ministry said ministerial and vice-ministerial reviews were examining whether the delivery plan could meet the agreed milestones. It also reported weekly discussions between the countries' industry ministries, alongside work on choosing a replacement construction contractor.2
Technical qualification remains a separate hurdle
An August briefing by Czechia's Confederation of Industry identified another condition for participation: selected safety-related packages require ASME certification, the standards framework of the American Society of Mechanical Engineers. The confederation said applicants could register before completing certification, provided they had started the process and could demonstrate the required quality systems and capability. Certification would be needed by selection of the winning bidder.4
The same briefing described support for smaller companies buying certification-related consultancy, with applications scheduled from 4 September 2026 to 1 February 2027. That assistance can help a firm qualify; it does not award a supply contract.4
The confederation listed forthcoming opportunities in pumps, cooling equipment, hydrogen monitoring and combustible-gas detection. The ministry's project update separately identified transport infrastructure for oversized components, demonstrating that the supply chain extends beyond the reactor equipment itself.4 3
The Korean ministry said the governments intended another ministerial implementation meeting before the end of 2026. The immediate open question is whether the revised construction procurement will give Czech businesses the scope, responsibilities and timetable they say they need to commit resources.2 1