Iron ore development around Mayoko in the Republic of the Congo depends on restoring a reliable route to the Atlantic coast. Ulsan Holding's Turkish-language update of 5 June 2026 describes railway rehabilitation and equipment procurement alongside plans for a processing plant at Mayoko-Moussondji. It presents these as development steps, rather than evidence of sustained export shipments.1
Ulsan said the planned initial processing capacity was approximately 2.5 million tonnes a year, with later expansion envisaged. The company also described future pellet, direct-reduced iron and steel facilities. These are different stages of processing, and their proposed capacities cannot simply be added together as extra tonnes of exports.1
Transport links the mine to the customer
Prospect's report of 21 July 2026 describes a planned US$240 million investment in logistics supporting the project. Its account connects the investment to the railway between Mayoko and Pointe-Noire and to the supply of locomotives and wagons. The report concerns an investment plan and infrastructure preparations, rather than a verified record of completed annual deliveries.2
That route matters because the mine and the export port occupy different parts of the supply chain. In the reported plan, railway work is necessary to move ore towards the coast, while rolling stock determines how it can be carried. Announcing extraction capacity alone therefore does not establish the quantity that can be delivered to an overseas customer.1 2
Nearby projects must be kept separate
The country's extractive-industry transparency report, published on 30 December 2025, distinguishes Ulsan's project from Sapro-Mayoko. It records an initial Sapro export of about 40,000 tonnes in 2019 and says no further exports had occurred by the report's account, citing railway deterioration and financing constraints. That historical statement is not a complete record of subsequent developments.3
The report says both projects depend on the Congo-Ocean Railway corridor and highlights the need for coordination. Its account of a proposed increase in Sapro production is a target tied to financing discussions, not proof of output. Treating the neighbouring projects as a single operating mine would obscure those differences in ownership, development and shipment history.3
Steel would change the product being sold
Congolese state news agency ACI reported on 10 April 2026 that Ulsan planned a steel plant in the Loango special economic zone. It attributed the proposal to the company's management, which described its objective as follows.4
produire sur place de l'acier
Produce steel locally.4
The proposed plant would move the commercial offer beyond unprocessed ore. ACI reports expected industrial and employment benefits, but these remain the company's expectations. The evidence still needed is confirmation of commissioning, transport availability and actual shipments, so buyers can distinguish a planned integrated steel business from an operating source of ore or finished material.4