Budapest-Belgrade railway: freight runs, passenger trains await December

The Chinese-built Hungarian section has carried freight since 27 February 2026. Hungary's transport minister said in October that passenger trains to Belgrade could start in December; Serbia's operator names 13 December.

Companies and supply chains 18 November 2026

The Hungarian section of the Budapest-Belgrade railway, a flagship project of China's Belt and Road trade and infrastructure initiative, has carried freight since 27 February 2026, but the sources opened for this article do not report that passenger trains have started on it.3 Hungary's transport minister, Dávid Vitézy, said on 8 October 2026 that testing of the train-control system was complete and that international passenger service could begin in December.1 4 The head of Serbia's passenger operator has since named 13 December 2026, according to Hungarian press.5

What China's side says the line is

Xinhua, China's state news agency, called the line a landmark project of China and Central and Eastern European countries building the Belt and Road together, and the first to match Chinese railway technology and equipment with the European Union's rail interoperability rules.3 It reported that the Hungarian section is about 158.6 kilometres long, electrified for mixed passenger and freight use, with a design speed of 160 km/h. It was built by units of China Railway Group with Hungarian companies, and construction began in July 2020.3 When the full line opens, Xinhua said, the rail journey between the two capitals should fall from eight hours to about three and a half.3

匈牙利当地时间27日零时许,一列货运列车从匈牙利首都布达佩斯的费伦茨城火车站驶出,标志着匈塞铁路匈牙利段正式开启货运运输。

At about midnight on the 27th, Hungarian time, a freight train left Ferencváros station in the Hungarian capital, Budapest, marking the formal start of freight transport on the Hungarian section of the Hungary-Serbia railway.3

Why passenger service slipped

European Western Balkans, a regional news site, reported that János Lázár, the former construction and transport minister, said in December 2025 that the line would open on 20 February 2026. The date was then moved to between the end of February and 15 March, and then to Easter. None of these was met.2

The same report gave two obstacles: certifying the signalling and safety system installed on the Hungarian section, and harmonising the systems used in Hungary and Serbia. The construction contractors had left in spring 2026 after finishing the infrastructure works.2

Prime Minister Péter Magyar said at a press conference on 16 July 2026 that passenger service should start within the next one or two months, without giving a date.2 That window also passed.

The October announcement

On 8 October 2026, Vitézy said the European Train Control System (ETCS), the signalling that automatically supervises train speed, had been successfully completed on the Hungarian section after a full-load test over the weekend.1 4 What remained, he said, was the contractor's final adjustment of the track, work of nearly two months that prepares the line for 160 km/h. The suburban section between Ferencváros and Kunszentmiklós-Tass was due by the end of October.1

If everything went to plan, he said, domestic passenger trains could start in the second half of October 2026 and international trains in December.1 Xinhua's financial service reported the same statement with one condition attached to the international start.4

维泰齐表示,如果匈塞铁路匈牙利段国内客运服务初期运行顺利,计划将于12月开通布达佩斯与塞尔维亚首都贝尔格莱德之间的国际客运服务。

Vitézy said that if domestic passenger service on the Hungarian section runs smoothly at first, international passenger service between Budapest and the Serbian capital, Belgrade, is planned to open in December.4

European Western Balkans quoted Vitézy as calling the remaining work "the usual, pre-planned final phase of work before the new railway line opens to traffic".1

Serbia's side names a date

The Hungarian news site 444.hu reported on 25 October 2026 that Ljubiša Pejičić, acting director of the Serbian passenger operator Srbija voz, had announced that international fast trains between Belgrade, Budapest and Vienna would start on 13 December 2026, when the new timetable takes effect.5 According to the report, he said the Serbian side was ready and that the Hungarian side had asked for further checks.5

A Belgrádból Budapestre szóló jegy várhatóan 35 euróba, míg a Bécsbe szóló 43 euróba kerül majd.

A ticket from Belgrade to Budapest is expected to cost 35 euros, and one to Vienna 43 euros.5

The 444.hu report repeated Vitézy's October timetable but did not say that domestic passenger service had begun.5

What remains open

None of the five sources confirms that the domestic start planned for the second half of October 2026 took place, and the 13 December date comes from the Serbian operator, not from the Hungarian government.1 5 The next checkpoints are a confirmed first domestic passenger train on the Hungarian section and the timetable change on 13 December 2026.

Sources

  1. European Western Balkans. Budapest–Belgrade high-speed passenger trains expected to launch in December. 8 October 2026Independent camp · press
  2. European Western Balkans. Budapest–Belgrade passenger trains to launch within one or two months. 20 July 2026Independent camp · press
  3. Xinhua. 匈塞铁路匈牙利段正式开启货运运输 (Hungarian section of Hungary-Serbia railway formally starts freight transport). 27 February 2026China's camp · state media · in Chinese
  4. Xinhua Finance. 匈塞铁路匈牙利段欧洲列车控制系统测试顺利完成 (European Train Control System testing successfully completed on Hungarian section of Hungary-Serbia railway). 8 October 2026China's camp · state media · in Chinese
  5. 444.hu. Megvan, mikor fut be a belgrádi gyors (Now we know when the Belgrade express arrives). 25 October 2026Hungary's camp · press · in Hungarian

All articles