Australia's Scarborough gas project was 99% complete at the end of September 2026, excluding modifications to Pluto's existing first processing train, Woodside reported in its latest quarterly update. The company still targeted its first liquefied natural gas cargo in the final quarter of 2026. That commissioning milestone approaches alongside a Japanese winter-supply contract beginning the following year.1 2
Japan has bought a seasonal delivery commitment
JERA's Japanese announcement of 15 January 2026 records a binding agreement with Woodside replacing the previous nonbinding understanding. From fiscal 2027, JERA will buy three cargoes, approximately 200,000 tonnes, annually for five years during December to February. Delivery is to the destination under the contract's delivered-ex-ship terms.2
The buyer explains why timing matters. Gas-fired generation responds to peak demand and seasonal variation as renewable generation expands. Competition for liquefied natural gas, or LNG, also intensifies during the European and Asian winter. JERA describes the procurement need as:
安定的かつ柔軟に確保
Secure supplies reliably and flexibly.2
A portfolio contract does not fix every cargo's origin
Woodside's matching announcement says the winter volumes can come from its global portfolio, naming Scarborough, North West Shelf, Pluto and Louisiana LNG once operational. The contractual buyer and delivery season are specified, while the physical source can vary. Counting the entire winter agreement as guaranteed Australian export tonnage would therefore overstate what the announcement establishes.3
Woodside also distinguishes this supply agreement from JERA's earlier acquisition of a 15.1% interest in the Scarborough joint venture. Equity ownership and a separate portfolio purchase are different commercial commitments. The January contract gives a seasonal delivery arrangement; it is not simply a restatement of JERA's share of field production.3
Japanese finance supported the Australian development
The Japan Bank for International Cooperation announced a loan to Woodside Finance on 30 May 2024, with its own commitment capped at US$1 billion within US$1.45 billion of cofinancing. The stated purpose was development of the Australian gas field alongside JERA's project company. This financing predates the winter supply contract.4
The bank said JERA's equity could provide up to approximately 1.2 million tonnes annually, while separately establishing discussions with Woodside about additional supply during periods of stronger Japanese demand, especially winter. The distinction explains how financing, ownership and seasonal purchases can support the same relationship without representing identical cargoes.4
Commissioning must become a shipment
Woodside's quarterly report describes gas entering the offshore system and trunkline, followed by introduction to Pluto's gas-treatment equipment. Work on the cold section, where liquefaction takes place, was still progressing. These are operating milestones, not confirmation that the first Scarborough export vessel had sailed. The immediate test remains that first cargo against the company's final-quarter target, ahead of the winter contract's start in fiscal 2027.1 2