Cauchari-Olaroz produced 9,550 tonnes of lithium carbonate in the third quarter of 2026, 3% more than in the previous quarter, Lithium Argentina reported on 10 November. The existing Argentine operation is generating output while an accelerated expansion remains conditional on regulatory approvals in Argentina and China. The planned additional production should not be counted as current supply.1
Current production and future capacity
The operator's shareholder reported year-to-date production of 28,490 tonnes and maintained annual guidance of 35,000 to 40,000 tonnes. These project figures are presented on a full-operation basis, not as Lithium Argentina's ownership share. The release also describes its sales-cost calculation at Buenos Aires port, with onward delivery to buyers' factories in China deducted from the sales price. That distinguishes mine output from the value captured along the export route.1
The expansion plan announced on 30 September envisages another 45,000 tonnes of annual capacity. Within that total, the company wants to accelerate an initial 10,000-tonne module using adsorption-based direct lithium extraction, a process for recovering lithium from brine. The first module is part of the wider expansion, rather than additional capacity to be counted twice.2
The company said engineering had begun in China ahead of manufacture, shipment and assembly in Argentina, while the required Chinese technology-export authorisation had not yet been obtained. It targeted the necessary approvals in the first half of 2027 and initial production in 2028. The accelerated schedule was not included in the scoping study's economic calculations. These are company targets subject to permission and execution.2
Investment approval has a different purpose
Argentina's economy ministry approved Minera Exar's application to the large-investment incentive regime, known as RIGI, through Resolution 825/2026. The measure was adopted on 4 June and published on 5 June. Its official description covers the investment plan for the Cauchari-Olaroz expansion in Jujuy, including an additional production line, brine wells, evaporation ponds and supporting infrastructure.3
The government's description calls the project an:3
AMPLIACION DE LA CAPACIDAD PRODUCTIVA INSTALADA
Expansion of installed production capacity.3
Approval of that investment framework establishes the project's treatment under the Argentine regime. It does not demonstrate that the equipment has arrived or that the extra capacity is operating.3
The separate technology and permitting conditions remain explicit in the company's development timetable.2
National growth is already measurable
Argentina's statistics agency INDEC reported 9,798 tonnes of processed lithium carbonate in September, up 6.5% from the same month in 2025. Output over January to September was 35.4% higher than a year earlier. Those national figures cover a different period and production base from the quarterly Cauchari-Olaroz report, so they cannot be added together. They establish existing sector growth while investors await the approvals and construction milestones needed to turn expansion plans into further physical supply.4